1992-14700-Minutes for Meeting April 20,1992 Recorded 5/6/199292-14700 0118-0305
PUBLIC HEARING MINUTES
,_ L: � . I i
APPEAL OF KLIPPEL SITE PLAN APPROVAL' .:�
DESCHUTES COUNTY BOARD OF COMMISSIONERS,0'f
April 20, 1992
Chairman Maudlin called the meeting to order at 7 p.m. Board
members in attendance were Dick Maudlin, Tom Throop and Nancy Pope
Schlangen. Also present were: Rick Isham, County Counsel, Bruce
White, Assistant Counsel, and David Leslie, Planner.
Before the Board was a public hearing to consider an appeal of the
Hearings Officer's approval of Bend Aggregate and Paving Company's
site plan for surface mining at the Klippel site.
Chairman Maudlin opened the public hearing and asked for a staff
report.
Dave Leslie said he had received two additional letters of
testimony since the staff memorandum to the Board which would be
added to the existing 67 exhibits. In his memorandum dated
April 13, 1992, he provided a summary, analysis and recommendations
on the seven issues contained in the notice of appeal. From his
report, he wanted to highlight a few items. Under the category
"truck traffic heading south on Johnson Road, he wanted to point
out that the decision indicated that the ESEE impacts would need to
be met. The Hearings Officer altered one of those ESEE conditions,
which Mr. Leslie felt was an improper change. He recommended that
the Board: (1) change that condition to reflect the actual ESEE
language that the applicant was required to consult with Public
Works, (2) make the findings in the Board's decision that this
consultation occurred and that the authority for the Road
Maintenance Agreement was contained within the Deschutes County
Zoning Ordinance. Because the ESEE condition was changed to
reflect that the Road Improvement Agreement needed to be met, that
language should be pulled out and given its own separate condition
#17. Also in the last paragraph under the same heading, the
decision by the Board should reflect that it was a staff
recommendation (not an appellant recommendation) that screening of
resource material temporarily not be allowed to occur until trucks
could head south. On Page 8, #5 regarding the requirements of the
ODF&W, the ESEE analysis required that a winter closure plan be
finalized with them. He thought the appellants correctly pointed
out that there was no direct link in the conditions that this plan
would need to be implemented and followed through. Therefore, he
recommended that page 9 of the findings and decisions be revised to
clearly state that the developer would implement and follow the
Klippel Acre Wildlife Mitigation Plan. Condition #8 of the
Findings and Decision needed some corrections in the numbering of
the conditions: conditions 3, 10, 11 from the ESEE remained the
same; add conditions 2A and 2C regarding an access permit from
PAGE 1 MINUTES: 4-20-92 " " FWD
KE C D
19-1�t
0118-0306
Public Works and the requirement to pave 200 feet of their access
road; delete reference to items 2B and 2E; and where it said 6, 7,
and 14, add 17 and 18. 17 concerned the road improvement agreement
and 18 (c) and (d) referenced the ODF&W plan. Concerning condition
#16, he suggested improving the language to change the last three
words "road maintenance agreement" to "bridge improvement
agreement. If the Board agreed with his recommendations, his
memorandum could be used as findings for their decision.
Chairman Maudlin asked for testimony from the neighbors of the
Klippel acres site.
Greg Hendrix, 716 NW Harriman, Bend, testified that he was an
attorney representing Mr. & Mrs. Andy Meswick and Mr. & Mrs.
Charles Allen and felt he was representing all of the neighbors who
had appeared and were on the notification list. He submitted a
supplemental memorandum and asked that the record remain open for
seven days to allow for additional written comment. His clients
didn't engage him until their appeal time had nearly expired, so he
had rephrased some of the objections. He felt that no one should
have to be $1000 to make an appeal to their elected public
officials. He pointed out that County staff had outlined the
mistakes made by the hearings officer, and so it was "bad public
policy" to require $1000 to appeal what might be mistakes. He
suggested that the costs be spread among all of the applications.
if someone wanted to make an appeal to LUBA or the Court of Appeal
it cost $100; to appeal to the Supreme Court of the United States
it cost nothing. Commissioner Throop pointed out that the Budget
Committee was the appropriate place to raise this issue. Mr.
Hendrix went on to raise what he considered the "moral" issue. His
clients attended the surface mining hearings and their strong and
adamant recollection was that when the Klippel Acres site was
discussed at the ESEE, the Board talked about screening and
crushing as the same kind of "processing" operation. Both were
considered "processing" under state law. When the ESEE analysis
was passed and approved, it stated that only crushing would be
excluded at this site. Throughout the application process, the set
back on the screener was discussed as 250 feet. He felt this was
an error, and that the correct set back was found in Deschutes
County Zoning Ordinance 18.52.090(B) "any storage and processing
not occur within a quarter mile of a sensitive use or structure.
The ordinance did describe screening and crushing as different
activities, however the ordinance did not define "processing."
Therefore, he felt the state law definition of "processing" would
apply. ORS 517.750(11) defined processing as "including but not
limited to crushing, washing, milling, and screening." He,
therefore, contended that the County's ordinance required that
processing operations, including screening, have a one-quarter mile
set back. It was the applicant's burden to show that the screening
site was not within one-quarter mile of homes. Since the
application said they were not within 250 feet, he felt the
application needed to be denied, and the applicants needed to
PAGE 2 MINUTES: 4-20-92
0118-0307
refile the application and provide assurances and documentation on
whether the proposed screener was within one-quarter mile of a
sensitive use. Applicant's own map appeared to show that the
screener would be within the one-quarter mile set back.
Greg Hendrix continued that his second main issue concerned the
truck traffic. They were in favor of having the screening
temporarily stopped until the bridge was improved, however, they
really did not want screening on the site ever. On page 9, #7 of
the ESEE analysis, the applicant suggested that it would be
necessary to have 4.6 truck trips per hour for extracted rock, and
on Page 22 of the ESEE, the Board found that "approximately 4-6
trips" per hour would be an acceptable impact considering all the
balancing of the conflicting uses. The hearings officer's decision
on Page 11 discussed 12 trucks per hour. They felt this was a
fault in the hearings officer's decision which should be corrected
here. Everyone was bound by the ESEE analysis, so if they were
going to have more than 4-6 trips per hour, the applicants needed
to ask for an amendment to the ESEE analysis and the ordinance.
The applicants had indicated that they were going to use water to
keep the dust down. He didn't feel they could legally use
irrigation water to do this. If they were going to use water
trucks to provide the water, he felt they should have to include
the water trucks in the 4-6 truck trips per hour. If they didn't,
he felt they should have to amend the ESEE analysis to include
water truck trips. Therefore, until the ESEE was amended, they
should be allowed only 4-6 trips an hour including water trucks.
Dave Leslie asked applicants to supply this information at the end
of the December hearing, however it was never supplied to his
knowledge.
Greg Hendrix referred to Mr. Leslie's memorandum of April 13, 1992,
and said Mr. Leslie's analysis of sight screening was good. It was
their position, under Deschutes County's ordinance, that if the
supplied vegetation could not perform the site obscuring
requirement, then earthen berms had to be used to do so. The
Hearings Officer indicated that 6 feet of vegetation would not be
sufficient to meet the sight obscuring standard. Concerning the
Fish and Wildlife agreement, they agreed with Mr. Leslie, but
requested that it include a specific timetable for reclamation.
They wanted something included which would get the seed in the
ground in time for it to germinate. The agreement also did not
reflect the March 19, 1992, agency letter, where ODF&W highly
recommended that the closure period be increased to December to
April. There was no timetable in the Hearings Officer's decision
that limited operations to 5 -acres at a time. They felt that only
way to assure that what the County had in mind was actual
accomplished, was to have clear standards at this level. He agreed
that CRL, Inc. had a reputation as good corporate citizens, but
even good corporate citizens needed to have clear guidelines. If
the County's intention was to have the mining done in "nice,
surgical 5 -acre bites," then the approval process should be in 5 -
PAGE 3 MINUTES: 4-20-92
0118-0308
acre bites, i.e. they wouldget a permit to do 5 acres, when that
site was closed and reclamation completed, they could apply for the
next 5 -acres. They agreed with Mr. Leslie that the Hearings
Officer's decision failed to require consultation with Public Works
regarding the bridge and other road improvements. They felt the
decision should require that the applicant keep rock off the 200
foot section leading onto Johnson Road since rocks would spill out
onto the highway from this section. These rocks would create a
hazard for bicyclists. He didn't see anything about the water
rights being maintained on the property. They felt the water
rights should be preserved.
Chuck Allen, 19175 Klippel Road, Bend, said he had heard at a
previous hearing that mining could occur one-quarter mile from a
scenic highway. However, Mr. Leslie said they would not allow them
to mine the part which visitors could see from the highway. He
thought it was wonderful to take the visitors into consideration,
however, this mining was being allowed at the Klippel site "right
in front of our house." He didn't feel that was fair. He felt
strongly that screening should not be allowed on this site, and
that the Board had agreed there would be no processing on this
site.
Andy Niedzwiecke, 19425 Klippel Road, Bend, testified that he had
understood from the people who attended the hearings that
"processing" included screening. Now screening was being allowed
as a permitted use. He asked that the Board not allow screening on
this site. They already had a Coats mining operation on one side
of them. He tried to get some help from the County and the State
to monitor the noise level. The County, the State and the Sheriff
wouldn't do it, so there would be no control over the noise on this
site. He agreed that the water trucks should be included in the
total number of truck trips allowed on this site. He felt the
six-foot trees would not be adequate to obscure the site, nor would
a berm be pleasant to look at, so he felt larger vegetation would
be the best answer. They would also like to see a longer shut -down
period in the winter for the wildlife, and that application be made
for each 5 -acre increment being mined and reclaimed. He didn't
feel that a commercial operation should be allowed to use
irrigation water for dust control.
Bill Moore, 63394 Fawn Lane, Bend, testified that all of the
neighbors had assumed that processing included screening. He said
the 6 -foot vegetation would not screen this site from his view, and
it would have to be a "pretty significant earthen berm" to obscure
his view. He agreed that each 5 -acre parcel should have its own
separate approval.
John Homan, 19130 Klippel Road, Bend, testified that he was
concerned about the south -bound traffic. When he left for work at
5 a.m., he encountered log trucks coming from Shevlin Park and
Coats' aggregate trucks. The road was torn up and filthy already.
PAGE 4 MINUTES: 4-20-92
0118-0309
Trucks from the Klippel site would make matters worse. The road
was already narrow and with the heavy bicycle use, it was just a
matter of time before someone was seriously hurt. When the trucks
were on the up -hill portion of the road, there was a double yellow
line, but people would take the risk to get around the trucks. The
bus stop for the school children was right on Johnson Road, and
there was no place for them to stand back off the road. The
additional trucks made that situation more dangerous. He requested
that the trucks not be allowed to go south on this road, especially
since their business was north.
Sally Callan, 442 NW State Street, Bend, read the attached
testimony.
John Schubert, 62915 Nasu Park Loop, Bend, said he directed Biking
for a Better Community, a citizens group working to promote
bicycles as transportation in Deschutes County to preserve the
livability of this area by reducing air pollution and minimizing
road traffic. He agreed with the comments made by Sally Callan,
especially about the need to keep any additional traffic from
proceeding south on Johnson Road. He asked that the Board "keep
this County as bicycle friendly" as possible for transportation.
Chairman Maudlin asked for testimony from those opposing the
appeal.
Nancy Craven of Ball, Janek, Novack, 101 SW Main, Portland,
testified that she was an attorney representing Bend Aggregate and
Jim and Jerry Curl. She just received a memorandum from Mr.
Hendrix and requested that the record be left open to allow an
opportunity to respond. She was testifying in defense of the
Hearings Officer's decision. The County's ordinance indicated that
a site plan approval had to be granted if the ESEE standards were
conformed with and if the ordinance requirements were met. The
Hearings Officer and the staff concluded that the applicant had
satisfied those conditions. The only challenges to the site plan
which were appropriate were those which related to the standard of
approval which a site plan must meet. Any issue which was not
related to the conformance of an ESEE condition or an ordinance
requirement was not relevant to the case. She felt the appellants
were raising issues which either had already been decided by the
County or should have been raised at prior hearings. It was their
position that the Board must approve and could not deny an
application if the standards were or could be met. She felt a
review of the Goal 5 decision was important to this appeal. The
Board found that this site had a "very significant aggregate
resource." In the ESEE hearings, they considered a balance of
conflicting uses and impacts, and as part of that process, proposed
an operational plan which was accepted by the Board in the ESEE.
Bend Aggregate made that ESEE a part of their site plan
application. On page 8 of the ESEE for the Klippel site, the Board
made a finding accepting the proposed operational plan which
PAGE 5 MINUTES: 4-20-92
0118-x0310
included specifically "excavation, transport to the permanent
crusher area on site, crushing, screening, and reclamation." The
Board then limited the extent to which they protected the aggregate
resource by placing conditions in the ESEE to mitigate the impacts
on the neighborhood. One condition the Board imposed was to "allow
surface mining activities in accordance with the site operation
plan excluding a crushing operation on site." Because of this,
Bend Aggregate modified their operational plan to be consistent
with the ESEE by eliminating on-site crushing and left the
remaining components previously included in the original operations
plan which had been accepted by the Board. Their site plan
application satisfied all of the ESEE conditions set by the Board.
Therefore, they felt there were no grounds to deny the site plan
application. She went through the staff report in responding to
the appellant issues. They felt the appellants principal concern
was the screening and crushing. Appellants felt screening and
crushing were the same thing, and that when the Board precluded
crushing at the site, they really meant to prohibit screening also.
She felt the appellants had misinterpreted the Board's ESEE
decision and had failed to recognize the distinction between
crushing and screening. The Board accepted Bend Aggregate's
operational plan and developed ESEE conditions. The Board found
that the DEQ noise standards could be met by the plan and accepted
the expert report, however the Board decided to further protect the
conflicting uses by prohibiting on-site crushing "which generates
the highest level of noise of the various components of the
operation." She felt that quote recognized that Bend Aggregate's
operational plan included various components, one of which was on-
site crushing. If the appellant's wanted to eliminate screening,
they should have raised this issue during the ESEE review process.
The ordinance specifically distinguished between screening and
crushing and they had different standards for operation. In all of
the meetings she had with County staff, these issues were
distinguished, and the industry had wished they had not been
distinguished. By eliminating crushing, the Board satisfied its
intent to prohibit a commercial operation at the site, drastically
reduced truck traffic into Bend, and eliminated the highest noise
generator.
Ms. Craven said appellant's second issue concerned the south -bound
traffic. She said this was addressed by the Board in the ESEE and
could not be addressed under the standard for review of this
application. In the ESEE, the County analyzed the transportation
component of Bend Aggregate's original operational plan and found
that protection of the aggregate resource "may have an impact on
the transportation infrastructure, but that the close proximity to
Bend minimizes this consequence and preserving the resource near
the major market area makes sense since less infrastructure is
affected." The Board also found that even if traffic on Johnson
Road exceeded the projections in the plan, any impact could be
mitigated by improvements or fees in lieu of improvements. She
felt the application was consistent with the ESEE conditions and
PAGE 6 MINUTES: 4-20-92
0118-0311
all ordinance requirements concerning traffic, transportation and
road impacts. She agreed with the staff report that the Board had
no authority to preclude their use of Johnson Road, and that Bend
Aggregate had consulted with Public Works as required under ESEE
condition #10. They had negotiated a road maintenance agreement
with the County which had not yet been finalized, but would require
Bend Aggregate to submit materials to the County in an amount based
on their pro rata percentage usage of the road, which was
consistent with the Ordinance requirement.
Ms. Craven said appellants third concern was vegetative screening.
She agreed with the staff report that the ordinance standard was
specific, and they would meet the six-foot high, six-foot center
standard. Concerning the request that Bend Aggregate provide trees
to be placed on appellant's property, she agreed with the staff
that there was no provision in the ordinance for requiring actions
on property outside the control of the applicant. Concerning the
earthen berm, she said there was no standard in the ordinance for
the earthen burn unlike vegetative screening. She didn't feel the
term "obscure" could be read to mean total concealment.
Ms. Craven said the fourth appellant's issue dealt with possible
water pollution. Bend Aggregate had submitted to the County expert
reports from CH2M HILL and ODF&W which indicated there would be no
adverse environmental consequences to surface or ground water
resources in the vicinity. In the ESEE, the County accepted these
reports regarding Tumalo Creek.
Ms. Craven said the fifth issue concerned a winter closure plan
with ODF&W. Bend Aggregate had worked with ODF&W to finalize a
winter closure plan which had been submitted to the County. It
included a winter closure report and specific measures for
planting, forage and screening. They had no objection to staff's
suggestion that a condition be imposed that Bend Aggregate would
have to comply with this winter closure plan. Last weekend Bend
Aggregate began implementing the ODF&W agreement by planting 1,100
trees.
Ms. Craven said that claim number six concerned the enforcement of
water management regulations. She agreed with staff that Bend
Aggregate had submitted evidence to show compliance with all water
management regulations. She said the issue of property values had
been previously resolved by the Board on page 22 of the ESEE where
the Board accepted the Assessor's office analysis that no evidence
of decreased property values would result.
In summary, Bend Aggregate's position was that the appellant's
claims could not be sustained and failed to address the relevant
standards of approval which covered site plan approval requests.
She said appellants were not happy with the ESEE or the zoning
ordinance language, however these issues should have been dealt
with during the adoption of the ordinances. Concerning the one -
PAGE 7 MINUTES: 4-20-92
0118-0312
quarter mile set back for screening, it was her understanding from
her client and discussions with Dave Leslie that the one-quarter
mile limitation was used --not 250 feet. She said that was
documented in the noise report which was a part of their
application and indicated that the screener was more than 1/3 mile
from any residences. If the Board wanted Bend Aggregate to verify
the set back of the screener, they would do so. They objected to
any consideration of a separate application for each 5 -acre parcel.
That was not provided for in the ordinance, and the application was
made as one site, and it had always been one site. Concerning the
comments on the impacts on bicyclists on Johnson Road, the Board
had already considered that in the ESEE analysis and determined
that the fee provision adequately mitigated that concern. Again,
this issue was previously addressed in the ESEE and was not a
subject which the Board could review again as part of site plan
approval.
Chairman Maudlin said it was his suggestion that crushing be
excluded on this site. Generally speaking, when a crusher crushed
rock, it didn't dump it on the ground but ran it through a serious
of metal screen for sizing."That is not what the screening is
that we're talking about here." One of the reasons the Board
wanted no crushing on this site was to reduce the traffic south on
Johnson Road. He asked Bend Aggregate what they were going to
screen which didn't have to go through a crusher.
Jim Curl, Bend Aggregate owner, said the screen plant would screen
and separate the aggregate which was below 1-1/2 inch in size.
Anything above that size would be hauled to Tumalo for crushing.
This screening would eliminate some of the hauling to Tumalo since
the 1-1/2 inch and below would go directly to Bend for use in ready
mix concrete. They would run two, ten -yard dump trucks to the
ready mix plant on a daily basis during the week. Occasionally a
third truck would be used. Chairman Maudlin asked if they would
screen everything on the Klippel site before it was hauled to the
plant. Jim Curl said everything above 1-1/2 inch would go over a
scalping screen and into a pile which would then be delivered to
the Tumalo plant. All of the rock went through the screening plant
and was sized in one screening operation.
Commissioner Throop asked him to describe the screening operation
in more detail and asked if it had any moving parts. Jim Curl said
the screen was motorized and shook the rocks through the screen.
Screening plants were sold separately from crushing plants and
there were a number of operations which only did screening.
Chairman Maudlin asked for rebuttal testimony.
Greg Hendrix said he didn't hear Jim Curl say how much rock would
be screened. He said if the Klippel neighbors were stuck with the
ESEE, so was CLR; and the ESEE had a finding of approximately 4-6
trucks trips per hour which he felt had to include water trucks.
PAGE 8 MINUTES: 4-20-92
0118-031.3
The transcript from the first hearing showed that the applicants
were asked to supply information on the water trucks which was
never supplied. He didn't feel there was anything in the Ordinance
which wouldn't allow the permit process to go in steps. The best
way to handle enforcement was to have things spelled out at this
level. He felt that if the intent of the Board was to have this
site mined in 5 -acre increments, then why not require that the
approval be done in 5 -acre increments also. In the Hearings
Officer's findings on Page 8, Section 5, the only discussion was
that minimum use set backs were at least 250 feet from noise and
dust sensitive uses such as residences. That was the only place
where the Hearings Officer's findings refered to any minimum use
setbacks. Using the map they submitted, there were a couple of
houses within one-quarter mile. It was applicant's burden to show
they were not within one-quarter mile, and they haven't show that.
Concerning applicant's ability to pay a fee rather than make
improvements to the road, he questioned if that was the best way to
go. If their trucks were over and above the use which caused the
degradation of the road shoulders, why should they only have to pay
for their proportion of the use. When a shopping mall was sited,
the developer had to pay the full costs of upgrading the roads.
Bend Aggregate paying a proportional fee would not make the road
better or safer. The language said "fee or improvements," so if
the County allowed trucks to go south, he felt they should do
improvements to the road. He pointed out that if there was no
screening on this site, all of the trucks would go north, so all of
the concerns about impacts on Johnson Road would no longer be
issues. Or, if there was going to be screening on the site, then
they should have to improve Johnson Road to the arterial standard.
John Homan testified again that he used to work for crushers. He
suggested the Board visit a screening site. There would be a
series of screens and washing ponds which would require
reclamation. The rubber on the screens would eventually be worn
off. He knew that the screening plants were really noisy.
Chuck Allen said he used to be in the ready mix business, and
unless the screeners had changed, the rock hitting together to get
to the first screener made a tremendous amount of noise and dust.
There also had to be conveyor belts or something to get the rocks
up to the top screener and conveyor belts at each screen. He asked
that the Board take that into consideration.
Andy Niedzwiecke said he lived across from the R.L. Coats operation
and his wife had an opportunity to tour the operation. His wife
said the screener was very, very loud.
Paul Rugloski, 19155 Klippel Road, Bend, testified that he thought
the approval restricted any stockpiling on the site. If they
screened on site, there would have to be stockpiling. He didn't
feel that keeping the dust down during the screening process had
been adequately addressed.
PAGE 9 MINUTES: 4-20-92
0118-0314
Bill Moore said everyone was just playing with semantics. He
hadn't heard discussions on crushing and screening, he had heard
discussions on processing which he thought included crushing and
screening. He didn't know what a scalping pile was, but wasn't it
stockpiling. How could they barter for the maintenance costs? He
was concerned about how the noise standards would be enforced.
Nancy Craven referred to page 7 of Bend Aggregate's application
where it indicated they were one-quarter mile from any nearby
residences, and it also referred to that in the noise report. She
referred to the ordinance where it discussed fees in lieu of
improvements, and said Bend Aggregate did exactly what this Board
told them to do which was to meet with Public Works concerning
Johnson Road. She said this application was not like building a
subdivision and should not be treated like it was. Concerning
dust, the Hearings Officer imposed conditions on them which
required meeting DEQ noise and dust standards. There would be a
water truck on site as indicated in their application, and that
water truck would need to make two trips a day. There was nothing
in the ordinance to allow the Board to set up separate approvals
for each five -acre area. It was clear that when the Board
eliminated the crushing on this site, Bend Aggregate had to modify
its operational plan to delete crushing. There would be two trucks
traveling to Bend and there would be four trucks operating to
Tumalo. Each would be making round trips. They anticipated there
would be approximately three trips an hour to Bend and four trips
an hour to the Tumalo plant. They felt this satisfied the changes
which were made in the ESEE resulting from the Board's decision.
Commissioner Throop asked if a "trip" was one way or two way. Ms.
Craven said two way. Commissioner Throop said that would be two
round trips to Bend and four round trips to Tumalo. Ms. Craven
said there would be two trucks operating taking the screened
material to Bend, and each one would make three trips an hour.
Chairman Maudlin said no matter how fast they drove they couldn't
make three trips to Bend and back in one hour. Mr. Curl said that
two would be more likely. Ms. Craven said when they set the trip
figures, they set them at the maximum amount possible for the noise
analyst to consider, and they were still able to meet noise
standards. So these trip figures were the maximum number, and they
would probably be below that number. Commissioner Throop asked her
to respond to the ESEE limitation on 4-6 truck trips. Ms. Craven
said the truck trips which were described in the ESEE were based on
the operation which was then proposed which included crushing on
site. The operation as modified by the Board's decision did not
include crushing on site. The numbers which she just clarified for
the Board would be different than those provided for in the ESEE,
although she felt there was no ESEE condition of approval which
specifically limited the number of truck trips. When she made
comments on the ESEE, she was referring back to the body of the
ESEE to attempt to clarify Commissioner Maudlin's original motion
concerning the crushing on site. She said the Board was obligated
PAGE 10 MINUTES: 4-20-92
under the ordinance standards to
were relevant to the site plan
already met those. She said
additional "goal posts for us to
0118-031.5
apply only those standards which
approval, and the applicant had
the Board could not now raise
jump through."
Bruce White said that in Dave Leslie's memo he asked the Board to
clarify what the Board felt the screening standard meant.
Specifically, to what extend did the screening operation need to be
obscured? If the Board felt that the standard meant completely
obscured, there might be a question as to whether six feet of
vegetative screening would be adequate.
Dave Leslie said the winter closure plan was submitted to the
County with a letter from Norm Bahrens, ODF&W, and the letter
showed support for this closure plan including the time period of
closure. The maintenance of water rights was covered under the
requirement to meet the ESEE conditions. In addition to the
comments from the applicant's attorney regarding the ESEE
statements on the set back, there was a comment in the Findings and
Decision on Page 8 which indicated that based on the submittals
from the applicant, staff had determined that the one-quarter mile
set back was met. He did not believe that Public Works would agree
with Mr. Hendrix's statement that if there was no screening on this
site, there would be no impact on Johnson Road, since trucks would
still head north on Johnson Road to the Tumalo plant. The road
improvement agreement was intended to cover both directions of
travel. Concerning the person who testified about a restriction on
stockpiling, if that impression came from his earlier statements,
he wanted to point out that he was recommending that the associated
stockpiling not be allowed until screened material could be carried
south.
Chairman Maudlin said that additional written testimony would be
accepted until Monday, April 27, 1992, at 5 p.m. The Board would
make their decision on Wednesday, April 29, at 1:30 p.m. No
further verbal testimony would be taken at that meeting.
Chairman Maudlin closed the public hearing.
DATED this 1 �' day of n i , 1992, by the Board of
Connissioners of Deschutes County Or%g n.
AT T:
L,d� Z! C!i�,
Recording Secretary
PAGE 11 MINUTES: 4-20-92
Tom /ThrooU. 6Commiss
Nancy Pog e\ SchXa_ ngen, Commiss
PUBLIC HEARING SPEAKERS' LISTI
11`�,�,� s
_
PUBLIC HEARING TOPIC: i + pOe, 14 -(f
DATE: —TIME:
NAME ADDRESS r-, MY I ZIP
11.
12.
13.
14.
15.
16.
17
18
19
RECEIVED
APR 2 0 1992
Any kf_'
01 1.—Otli7
TESTIMONY
by the
DESCHUTES CO. BICYCLE ADVISORY COMMITTEE
on the Klippel Pit Operations Appeal
April 20, 1992
As Chair of the Deschutes County Bicycle Advisory Committee it
is my responsibility to address changes in the County that could
affect the ease and safety while using bicycle routes within the
county. We, the committee, believe it is important that you
recognize the very heavy use of this route by bicyclists and the
impact your decision will have on these citizens. This route is
used by visitors to the area as well as by local riders.
The loop from Downtown Bend out Shevlin Park/Johnson Roads and
returning on O.B. Riley Road is very likely the most heavily ridden
loop in all of Deschutes County, and probably in Central Oregon. It
is beautifully scenic, not too long or difficult and relatively
lightly travelled by automobiles.
There is some truck traffic along Johnson Road, already,
hauling gravel for the Highway 97 widening project. The effects of
this increased use by the loaded belly dump trucks are already
visible on the roadway. The very narrow shoulders are beginning to
break down, and along the ridge line before Johnson Road drops down
into the Deschutes Canyon there is a distinct swale where a culvert
for an irrigation side ditch is breaking down. These are problems
which will be exacerbated with the increased truck traffic from the
Klippel pit. They are also problems that increase the danger for
bicyclists sharing the roadway.
The safety issue was further underscored a week ago when a
rider was caught in the frightening situation of being passed by a
belly -dump truck on a corner. Had there been an oncoming car at
that moment there's no telling what would have happened. This road
is narrow and windy with no shoulder to speak of. The increased
truck traffic makes it more dangerous.
We remind you that bicycling is encouraged as a mode of
transportation in the State of Oregon Transportation Plan. The law
states that bicycles shall be considered in use and design of the
roadways.
Johnson Road is classified as a rural arterial (Shevlin Park
to Tyler Road) or collector (Tyler Road to Tumalo Reservoir Road).
The Deschutes County Bicycle Master Plan calls for either of these
roadways to have a minimum of four foot shoulders. In the absence
of shoulders there should be fourteen foot travel. lanes. The
current width of Johnson Road is generally at 231, under existing
county standards.
0118-0318
Klippel Pit Operations Appeal
Deschutes County Bicycling Advisory Committee
April 20, 1992
Furthermore, with tourism our second largest industry in
Deschutes Co. it is important not to jeopardize our most popular
bicycling routes. That delicate balance between growth and
preserving those things that make Central Oregon an attractive
place to live and visit must be preserved carefully.
Given the above, we hereby recobmend the following:
1. That hours of operations at the Klippel Pit on Johnson Road
be restricted as recommended in the Decision No. 1(B). We
understand that this will also restrict truck traffic leaving the
area to those times.
2. That resource material spilled onto Johnson Road will be
minimized as recommended in the Decision Nos. 2 (D) and (E).
Furthermore, we recommend that Johnson Road be swept for debris
once a week on Fridays to ensure safety of cyclists as much as
possible.
3. That consistent (monthly) road maintenance be performed on
Johnson to repair surface potholes and degradations to the
shoulder. This should be included in the "Road Maintenance
Agreement" with Deschutes County Public Works.
4. That the number of truck round trips per hour from the
Klippel Pit be limited to a total of 4. This will lessen the
opportunity for conflicts between the trucks and other users of the
road.
5. Deschutes County should also seriously consider adding
shoulders to Johnson Road in the next year and a half. When
construction on the Bend Parkway begins, more motorists will be
using Johnson Road as a means to avoid the inevitable construction
delays. Conflicts between motorist:-, bicyclists and gravel hauling
trucks will become more corumion as use of Johnson Road steadily
increases.
6. Finally, we strongly recommend that truck traffic not be
allowed now or at any time in the future to proceed south on
Johnson Road. Your safety and road degradation problems will be
magnified 10 -fold, for cyclists, motorists, tourists, and others.
Thank you very much.
Respectfully submitted,
Sally Callan, Chair