2001-502-Resolution No. 2001-036 Recorded 6/21/2001VOL: CJ2001 PAGE: 502
RECORDED DOCUMENT
STATE OF OREGON
COUNTY OF DESCHUTES
*CJ2001-502 * Vol -Page Printed: 06/29/2001 16:27:35
DO NOT REMOVE THIS CERTIFICATE
(This certificate constitutes a part of the original instrument in accordance with
ORS 205.180(2). Removal of this certificate may invalidate this certificate and affect
the admissibility of the original instrument into evidence in any legal proceeding.)
I hereby certify that the attached instrument was received
and duly recorded in Deschutes County records.
DATE AND TIME:
DOCUMENT TYPE:
Jun. 21, 2001; 9:23 a.m.
Resolution (CJ)
NUMBER OF PAGES: 27
Lv� 0,., 0,-�
MARY SUE PENHOLLOW
DESCHUTES COUNTY CLERK
KEYpuNCHED
JUN 15 2001
OT A601005401M
BEFORE THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES COUNTY, OREGON
A Resolution Establishing a New System Development Charge
(SDC) Methodology and SDC, Fee Amount, and Adopting Capital * 3
Improvement Lists for Transportation and Park Improvements * 4
Within the Redmond Urban Growth Boundary, and Prescribing an
Effective Date of July 1, 2001.-
c', r
RESOLUTION NO. 2001-036
WHEREAS, the intergovernmental agreement dated June 23, 1998 between Deschutes ouhty and
the City of Redmond provides for joint management within the City of Redmond Urban Growth Boundary,
Redmond Growth Area and Redmond Area of Mutual Interest; and
WHEREAS, Deschutes County Code Chapter 15.12 and ORS 223.297 to 223.314 provide for the
establishment of system development charges (SDCs) by resolution; and
WHEREAS, Deschutes County had previously adopted Resolution 96-086 in 1996 which established
a system development charge for transportation within the Redmond Urban Growth Boundary outside the City
of Redmond, pursuant to County Code and state law; and
WHEREAS, the City of Redmond has been experiencing rapid growth, creating the need to update
its public facility plan, methodology, and corresponding transportation system development charge; and
WHEREAS, notice of the City of Redmond's consideration of an amended methodology for systems
development charges was provided as required by state law, ORS 223.304(5); and
WHEREAS, the City of Redmond City Council held public hearings on February 27, 2001; March
13, 2001; March 27, 2001; April 10, 2001; and May 8, 2001; and
WHEREAS, the Redmond City Council, after considering all testimony and evidence presented at
the hearings, authorized the establishment of a new public facilities plan and new SDC fees through the
adoption of Redmond Resolution No. 2001-10 and Ordinance No. 2001-04; and
WHEREAS, pursuant to the intergovernmental agreement, approval of the new City of Redmond
Public Facilities Plan and SDCs also requires approval by the Deschutes County Board of Commissioners
after a public hearing; and
WHEREAS, notice of the public hearing was published in the Bend Bulletin on May 27, 2001; and
WHEREAS, interested parties were notified of a change in systems development charges within the
Redmond Urban Growth Boundary; and
WHEREAS, the Deschutes County Board of County Commissioners held a public hearing on June
13, 2001; and
WHEREAS, it is necessary for good accounting practices to begin collection of updated SDCs at the
beginning of Fiscal Year 2001-2002 which is July 1, 2001; now, therefore,
BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES
COUNTY, OREGON, as follows:
Section 1. PURPOSE. This resolution shall establish new SDCs within the Redmond Urban
Growth Boundary, outside the City of Redmond. The purpose of the SDCs imposed by this resolution under
PAGE 1 OF 2 — RESOLUTION NO. 2001-036 (6/13/01)
authority of DCC Chapter 15.1.2, is to pay for a portion of the cost of capital improvements for transportation
and park improvements in the Redmond Urban Area, outside the City of Redmond.
Section 2. METHODOLOGY AND CHARGES. The Board hereby adopts, as the
methodology to establish systems development charges and charge rates for transportation and park projects,
within the Redmond Urban Growth Boundary, outside the City of Redmond, the methodology and charges set
forth in the City of Redmond Public Facilities Plan previously adopted by the City of Redmond Resolution
No. 2001-10 and summarized in the "Executive Summary Outline, Capital Improvement Program and SDC
Calculation", dated May 2001, marked as Exhibit "A," attached hereto and incorporated herein by this
reference.
Section 3. CAPITAL IMPROVEMENT PLANS. The Board hereby adopts Table 5-1, "Capital
Improvement Program" (transportation), dated May, 2001, and Table 8-4 "Redmond's Parks' Capital
Improvement List" (parks), dated 10-27-00, previously adopted by the City of Redmond Resolution No. 2001-
10, marked as Exhibits "A" and "D" to the Resolution No. 2001-10 and attached hereto and incorporated
herein by this reference.
Section 4. ANNUAL ADJUSTMENT OF CHARGES. Each year, the charges established
herein shall be automatically adjusted based on the annual average of the Construction Cost Index published
by the Engineering News -Record. The charges established above reflect the base year of 2001.
Section 5. EFFECTIVE DATE. The system development charges established pursuant to this
Resolution shall become effective on July 1, 2001. Until that time, the charges previously established shall
remain in effect.
Section 6. REPEAL. Upon the effective date for the systems development charges established
in this Resolution, Deschutes County Resolution 96-086 shall be repealed.
DATED this! 3 day of 4^ 12001.
ATTEST:
Tllm_�
Recording Secretary
BOARD OF COUNTY COMMJSSIONERS
OF DESCHUTES COUNTY GON
Tom De
Debnis R. Luke, Commissioner
ch el M. Daly, Co missioner
REVIEWED
,..,,..LEGAL COUNS11
PAGE 2 OF 2 - RESOLUTION NO. 2001-036 (6/13/01)
EXHIBIT "A"
PUBLIC FACILITIES PLAN
EXECUTIVE SUMMARY OUTLINE
CAPITAL IMPROVEMENT PROGRAM
AND SDC CALCULATION
Prepared by Mary Meloy
Redmond Public Works Director
Updated May 2001
TRANSPORTATION
FACTORS:
• Used official growth rate of 4.25%
• Transportation Capital Improvement Plan is based on implementation of the
projects over a 20 year period (Source: Redmond Transportation System
Plan (TSP)]
• TSP transportation forecasts were updated in 1999 to reflect future
residential, commercial and industrial traffic at 4.25% growth rate
• Cost estimates were prepared for each project (1999 dollars) and include
design, construction, right-of-way and contingencies
• Total cost of 20 year CIP projects is $96,642,900
SDC METHODOLOGY:
1) Of the $96,642,900, only the cost of arterial and collector "oversizing" is
eligible for SDC funding
Extra width and extra depth is eligible
Bike Lanes are eligible
Sidewalks are not eligible
Separated Bike Paths are not eligible if for recreation
2) SDC eligible costs were separately calculated for each project
3) Of the total cost ($96,642,900), $27,972,710 million was eligible for SDC
funding
4) This new methodology recommends using trip generation from the ITE
(International Traffic Engineer's) 6th Edition, Manual PM Peak Hour Trip
Rate, as a basis for calculating SDC charges, or applicant may have a licensed
traffic engineer prepare an estimate of trip generation for a particular use.
(City Engineer may accept or reject the traffic study.)
5)
6)
7)
Table 5-2 forecasts the increased trips over the 20 year period at 15,172
To get a cost per trip, divide the cost basis by the number of new PM peak
hour trips:
Cost basis of $27,927,710
# of New PM peak hour trips is 15,172
with ENR* Inflation z
* Engineering News Record
Cost of new trip $1841
$1905
Examples of Transportation System Development Charges for Various Land
Uses (Table 5-3)
TABLE 5-3
Examples of Transportation System Development Charges for Various Land Uses
Key: DU = dwelling unit
TGSF = total gross square feet
TGLA = total gross leasable area
Source: Trip Generation, 6th Edition, Institute of Transportation Engineers
F
PM Peak
Hour Trip
Total No.
Estimated
No.
Description
Size
Unit
Rate
of Trips
SDC Fee
210
Single -Family Residence
1
DU
1.01
1
$1,905
220
Apartments
40
DU
0.62
25
$47,625
240
Mobile Home Park
75
DU
0.56
42
$80,010
252
Congregate Care Facility (Senior Care)
50
DU
0.17
9
$17,145
565
Day Care Facility
10
students
0.86
9
$17,145
710
General Office Building
8,000
TGSF
0.00149
12
$22,860
720
Medical/ Dental Office
2,500
TGSF
0.00366
9
$17,145
814
Specialty Retail Center
4,500
TGSF
0.00259
12
$22,860
832
High-Tumover Sit-down Restaurant
3,500
TGSF
0.01086
38
$72,390
834
Fast -Food Restaurant with Drive -Through
2,500
TGSF
0.03348
84
$160,020
Window
912
Bank (with Drive -Up Window)
4,000
TGSF
0.05477
219
$417,195
820
Regional Shopping Center
100,000
TGLA
0.00374
374
$712,470
320
Motel
80
rooms
0.47
38
$72,390
130
Industrial Park
30,000
TGSF
0.00092
28
$53,340
140
Manufacturing
30,000
TGSF
0.00074
22
$41,910
150
Warehousing
30,000
TGSF
0.00051
15
$28,575
Key: DU = dwelling unit
TGSF = total gross square feet
TGLA = total gross leasable area
Source: Trip Generation, 6th Edition, Institute of Transportation Engineers
F
WATER
FACTORS:
• Used official growth rate of 4.25% and used final population figures as
distributed to each City by Oregon Office of Economic Analysis
• Water Capital Improvement Plan is based on implementation of adopted
Water and Sewer Master Plan
• A computer model was used to represent build -out conditions to determine
the size of pipelines, wells and reservoirs
• Cost estimates were prepared for each project (1999 dollars) and include
design, construction and contingencies
• Total cost of 20 year CIP projects is $27,026,910
SOC METHODOLOGY:
1) Water SDC consists of two parts; an improvement fee and a reimbursement
fee.
The improvement fee is designed to recover the cost of future capital
projects.
The reimbursement fee is based on the costs of capital improvements
already constructed or under construction.
2) Of the $27,026,910, only the cost of pipelines, wells and reservoirs
attributable to growth are eligible to be funded by SDCs
Pipelines over 8 -inch diameter have the cost increment exceeding 8 -
inch line attributed to SDCs
Pipelines to replace existing older pipelines are not eligible
New wells are considered 100% new capacity
Storage reservoirs over and above those needed to correct
deficiencies in the current system are considered new capacity.
3) SDC eligible costs were separately calculated for each project
3
4)
Of the total cost ($27,026,910), $17,995,900 was eligible for SDC funding
PART ONE: Determine Future EDU's
1) First determine how many equivalent dwelling units (EDU's) of future
capacity in the planned improvements for the 20 year period
2) Based on actual water use characteristics in Redmond, residential units use
61% of the water.
3) Based on the adopted Water and Sewer Master Plan there will be 15,047
residential EDU's in the year 2020 (Land Use, water capacity, and population
analysis)
4) Knowing that 15,047 EDUs equates to 61% of the water used, allows us to
project the total number of EDUs in the year 2020 as follows:
15,047 Residential EDUs
---------------------------- _
.61
Total EDUs
Residential EDUs
Commercial/Industrial EDUs
24,667 Total EDUs
24,667
- 15,047
------------
9,620
PART TWO: SDC's for Future Capacity (Improvement SDC):
1) Determine the growth EDU's as follows:
Total Future EDUs
Current EDUs
Growth EDUs
Il
24,667
- 8,823
-------------
15,844
2) To calculate the Improvement 50C, divide growth costs by growth EDUs:
Growth costs of $17,995,900
-------------------------------- _ $1136 per EDU
15,844 growth EDUs
PART THREE: Reimbursement 5DC for Existing Capacity
1) The Committee recommended not adding this fee to the improvement fee
2) To Calculate the Reimbursement SDC, divide the present unused capacity by
new EDU's
Present unused capacity of $2,766,958*
-------------------------------------------- _ $112 per EDU
24,667 new EDU's
*PFP Committee recommends using Book Value of assets rather than
factoring in inflation
3) Calculate the combined 5DC:
Improvement SDC $ 1,136
Reimbursement SOC 112
Combined SDC $ 1,248
with ENR Inflation $ 1,287
METER SIZE RECOMMENDED:
1) Charging the customer by the meter size is recommended for ease of
calculation
2) Charges are scaled upward with the size of meter (Table 6-8)
5
TABLE 6$
City of Redmond
Water System Combined Schedule
Improvement
Hydraulic Fee with
Capacity SDC Book Reimbursemen Improvement Inflation
Meter Size Ratio (gpm)(1) Value(2) t Fee (1999) Fee (1999) Increase(3) 2001
SDC(4)
Disc or Compound Meters
5/8 inch
1.0
$1,248
$112
$1,136
$1,175
$1,287
20
3/4 inch
1.5
$1,872
$168
$1,704
$1,763
$1,931
30
1 inch
2.5
$3,120
$280
$2,840
$2,938
$3,218
50
1 1/2 inches
5.0
$6,240
$561
$5,679
$5,875
$6,436
100
2 inches
8.0
$9,984
$897
$9,087
$9,401
$10,298
160
3 inches
16.0
$19,968
$1,795
$18,173
$18,802
$20,597
320
4 inches
25.0
$31,200
$2,804
$28,395
$29,377
$32,181
500
6 inches
50.0
$62,400
$5,609
$56,791
$58,756
$64,365
1,000
gpm = gallons per minute
(1) Based on Industry Reference Data
(2) At time information was developed, July 1999. Book Value=Reimbursement Fee+Improvement Fee
(3) Based on ENR Index of 6076 in July 1999 and 6286 in April 2001. 6286/6076=1.0346
Inflation increase applies only to Improvement fee, not to Reimbursement Fee
(4) 2001 SDC = Reimbursement Fee (1999) + Improvement Fee with Inflation Increase
WASTEWATER
FACTORS:
• Used official growth rate of 4.25% and used final population figures as
distributed to each City by Oregon Office of Economic Analysis
• Wastewater Capital Improvement Plan is based on implementation adopted
Water and Sewer Master Plan
• A spreadsheet model was used to represent build -out conditions to
determine the size of pipelines and treatment facilities
• Cost estimates were prepared for each project (1999 dollars) and include
design, construction and contingencies
• Total cost of 20 year CIP projects is $12,567,600
SDC METHODOLOGY:
1) Wastewater 50C consists of two parts; an improvement fee and a
reimbursement fee.
The improvement fee is designed to recover the cost of future capital
projects.
The reimbursement fee is based on the costs of capital improvements
already constructed or under construction.
2) Of the $12,567,600, only cost of pipelines, and treatment facilities
attributable to growth are eligible to be funded by SDC's
Pipelines over 8 -inch diameter have the cost increment exceeding 8 -
inch line attributed to SDC's
Pipelines to replace existing older pipelines are not eligible
New expansion at the existing treatment facility 60%eligible
3) SDC eligible costs were separately calculated for each project
7
4)
Of the total cost ($12,567,600), $5,382,325 was eligible for SDC funding
PART ONE: Determine future EDU's
1) First determine how many EDU's of future capacity in the planned
improvements for the 20 year period
2) Based on actual wastewater flow characteristics in Redmond, residential
units use 61% of the wastewater flow.
3) Based on the adopted Water and Sewer Master Plan there will be 15,047
residential EDU's in the year 2020 (Land Use, wastewater flow, and
population analysis)
4) Knowing that 15,047 EDUs equates to 61% of the wastewater flow allows us
to project the total number of EDUs in the year 2020 as follows:
15,047 Residential EDUs
---------------------------- =
.61
Total EDUs
Residential EDUs
Commercial/Industrial EDUs
24,667 Total EDUs
24,667
- 15,047
------------
9,620
PART TWO: SDC's for future capacity (Improvement SDC):
1) Determine the growth EDU's as follows:
Total Future EDUs 24,667
Current EDUs -8,573
------------
Growth EDUs 16,094
L
2) Calculate the Improvement SDC by dividing the growth costs by growth
EDU's
Growth costs of $5,382,324
-------------------------------- _ $334 per EDU
16,094 growth EDUs
PART THREE: Reimbursement 5DC for existing capacity
1) To calculate the Reimbursement 51)C, divide the present unused capacity by
new EDU's
Present unused capacity of $12,207,708*
-------------------------------------------- _ $759 per EDU
16,094 new EDU's
*Committee recommends using Book Value of assets rather than factoring in
inf lotion
2) Calculate the combined SDC:
Improvement SDC $ 334
Reimbursement 50C 759
Combined SDC $ 1,093
with ENR Inflation $ 1,105
METER SIZE RECOMMENDED:
1) Charging the customer by the meter size is recommended for ease of
calculation
2) Charges are scaled upward with the size of meter (Table 7-8)
E
TABLE 7-8
City of Redmond
Wastewater System SDC Combined Schedule
Improvement
Hydraulic Fee with
Capacity SDC Book Reimbursemen Improvement Inflation 2001
Meter Size Ratio (gpm)(1) Value(2) t Fee (1999) Fee (1999) Increase(3) SDC(4)
Disc or Compound Meters
5/8 inch
1.0
$1,093
$759
$334
$346
$1,105
20
3/4 inch
1.5
$1,639
$1,138
$502
$519
$1,657
30
1 inch
2.5
$2,732
$1,896
$836
$865
$2,761
50
1 1/2 inches
5.0
$5,465
$3,793
$1,672
$1,730
$5,523
100
2 inches
8.0
$8,744
$6,068
$2,675
$2,768
$8,836
160
3 inches
16.0
$17,487
$12,136
$5,351
$5,536
$17,672
320
4 inches
25.0
$27,324
$18,963
$8,361
$8,650
$27,613
500
6 inches
50.0
$54,648
$37,926
$16,722
$17,301
$55,227
1,000
gpm = gallons per minute
(1) Based on Industry Reference Data
(2) At time information was developed, July 1999. Book Value=Reimbursement Fee+Improvement Fee
(3) Based on ENR Index of 6076 in July 1999 and 6286 in April 2001. 6286/6076=1.0346
Inflation increase applies only to Improvement fee, not to Reimbursement Fee
(4) 2001 SDC = Reimbursement Fee (1999) + Improvement Fee with Inflation Increase
10
PARKS
FACTORS:
• Used Official growth rate of 4.25%
• Used Comprehensive Plan direction of park within I mile walking distance.
• Used Comprehensive Plan direction of acquiring Dry Canyon property and
other park properties before they are gone and become more expensive.
• For allocation of future costs to new development, consultants used the total
acres of parks to be built by four agencies - City, COPRD, Redmond School
District, and BLM. This spreads the responsibility of meeting NPRA
standards to all park providers in Redmond area. It does not load it all on
Redmond SDC's and Park taxes.
• Parks Capital Improvement Plan is based on implementation of projects over a
20 year period.
• Cost estimates were prepared for acquisition and development (1999 dollars).
• If the project is to meet a deficiency, 0% is attributed to growth or SDC's.
• If the project would be built to meet only the demands of growth it is
attributed 100% to growth or SDC's.
PARK UPGRADES (Improvements to existing park parcels)
If the upgrade would benefit both existing and future residents a
percentage was used based on a population growth in the UGB of 58.54%
(4.25%/year increase over the next 20 years.)
11
ADDITION OF NEW PARKS
For five new parks, the percentage of land area within the service area
(yellow circle) that is vacant land was estimated. Only that land area was used
to determine the percentage attributed to growth.
SDC METHODOLOGY:
1) Parks SDC's consist of an improvement fee only. Of the total cost of
$6,215,914 only Redmond projects were used and the percentage
attributable to growth was calculated totaling $4,201,913. (See Table 8-4 in
the Public Facilities Plan for a list of Redmond's Parks' Capital Improvement
List. )
2) An 5DC fee was calculated per new household (using residential units only.)
The PFPC recommended dropping the 51)C charge for Commercial and
Industrial uses.
3) To get a cost per household:
Cost basis of $4,201,913
-------------------------------------------- _ $ 203 per Capita
Population growth of 20,645 people
($203 per capita) X (2.24 persons per household) = $456 per Household*
*Cost per dwelling unit whether single family or multifamily.
12
REDMOND RESOLUTION
RESOLUTION NO. 2001-10
A RESOLUTION OF THE CITY OF REDMOND, OREGON ADOPTING A
METHODOLOGY AND PROJECT PLAN, ESTABLISHING NEW SYSTEMS
DEVELOPMENT CHARGES EFFECTIVE JULY 1, 2001, AND REPEALING
RESOLUTIONS 91-56,91-56,93-08,9M6 and 99-16.
WHEREAS, the City Council has previously authorized establishment of systems
development charges for the City through the adoption of Ordinance No. 2001-04; and
WHEREAS, the City has, pursuant -.to its Code and state law, had systems development
charges in place since 1982; and
WHEREAS, the City updated its systems development charges and related regulations
periodically over the past eighteen years; and
WHEREAS, the City has been experiencing rapid growth, creating the need to update
its capital improvement plans, methodology, and corresponding systems development
charges; and
WHEREAS, notice of the consideration of an amended methodology for systems
development charges was provided as required by state law, ORS 223.304(5);
NOW, THEREFORE, THE REDMOND CITY COUNCIL RESOLVES AS FOLLOWS:
Section 1. Capital Improvement Plan. The Council hereby adopts the "City of Redmond
Public Facilities Plan", dated July, 2001, as recommended by the Planning Commission,
as the Capital Improvement Plan for the City of Redmond for transportation, water,
wastewater, and parks improvements, as required by ORS 223.309.
Section 2. Methodology. The Council hereby adopts as the methodology to establish
systems development charges for the City, the methodology contained in the "City of
Redmond Public Facilities Plan", dated July, 2001, as recommended by the Planning
Commission. A copy of the report is on file at City Hall and is available for public
inspection, having been made available more than thirty days before Council's
consideration of this Resolution.
Section 3. Charges Established. The Council hereby adopts as the Systems
Development Charges for development within the City or connecting to the City's water
or wastewater systems, those charges shown in the schedules attached as exhibits to
this Resolution, incorporated herein by this reference, and denoted as follows:
Exhibit A: Table 5-1 and 5-113, Transportation Capital Improvement Program
Transportation SDC: $1905.00 per PM peak hour trip
Exhibit B: Table 6-813, Water System Combined Schedule
Water SDC: $1,287.00 per EDU
Exhibit C: Table 7-813, Wastewater System Combined Schedule
Wastewater SDC: $1,105 per EDU
Exhibit D: Table 8-4 and 8-413, Park Capital Improvement List
Park SDC: $458.00 per EDU
In calculating the Transportation SDC, the City may rely either upon the Institute of
Transportation Engineers Trip Generation Manual, current edition, or upon the estimate
of trip generation from a development as prepared and certified by a licensed traffic
engineer, in the City's discretion.
Section 4. Annual Adjustment of Charges. Each year, the charges established herein
shall be automatically adjusted based on the annual average of the Construction Cost
Index published by the Engineering News -Record. The charges established above
reflect the base year of 2001.
Section 5. Effective Date. The charges established pursuant to this Resolution shall
become effective on July 1, 2001. Until that time, the charges previously established
shall remain in effect.
Section 6. Repeal. Upon the effective date for the systems development charges
established in this Resolution, Resolutions 91-55, 91-56, 93-08, 95-06 and 99-16 shall
be repealed with no further action from the City Council.
PASSED by the Redmond City Council and APPROVED by the Mayor this � day of
2001.
Ed Fitch, Mayor, City of Redmond
. ATTEST:
Nancy 131ankensh ity Recorder
1`XHIBIT A
TABLE 5-1
Capital Improvement Program
F
Altematerrruck Route construction
$32,000,000
$20,000,000
$12,000,000
SDC
F1
Evergreen Avenue upgrade at US 97 Reroute
Total
State/
Total
Eligible
No.
Project
Cost
Federal
City
Funding (2)
Phase 1: 2000 to 2005
Hemlock Avenue upgrade at US 97 Reroute
$1,675,000
$1,675,000
Transportation
Demand Management Program
$20,000
$10,000
$10,000
$1,800,000
Street
Projects
US 97 north connection to US 97 Reroute
$550,000
$550,000
A
Airport Way reconstruction south of the airport
$1,356,100
$325,000
$1,356,100
$377,000
21A
Alternate Route Planning and Environmental Studies - Part 1
South Canal Boulevard construction from Sisters Avenue to Kalama
PCI
SE 19th Street construction from Airport Way to UGB
$1,325,000
$900,000
$1,325,000
$583,000
2
Evergreen Avenue and 5th Street Improvements
$0
$0
1
Highland Avenue and 5th Street Improvements
$25,000
$25,000
$800,000
6
Highland Avenue/Highway 126 Modifications at Highway 97
$4,300,000
$4,300,000
25A
Quartz Avenue improvements from South Canal Boulevard to 25th
Interchange to Highland Avenue
$3,450,000
$3,450,000
$1,518,000
Street
$850,000
$26,375,000
$850,000
$170,000
F
Altematerrruck Route construction
$32,000,000
$20,000,000
$12,000,000
F1
Evergreen Avenue upgrade at US 97 Reroute
$2,050,000
$2,050,000
F2
Antler Avenue upgrade at US 97 Reroute
$1,000,000
$1,000,000
$1,000,000
F3
Hemlock Avenue upgrade at US 97 Reroute
$1,675,000
$1,675,000
$1,675,000
F4
Maple Avenue/Negus Way upgrade at US 97 Reroute
$1,800,000
$1,800,000
$1,800,000
F5
US 97 north connection to US 97 Reroute
$550,000
$550,000
$550,000
F6
North Canal Boulevard upgrade at US 97 Reroute
$325,000
$325,000
$325,000
PC2
South Canal Boulevard construction from Sisters Avenue to Kalama
Avenue
$900,000
$900,000
$396,000
PC3
South Canal Boulevard construction from Kalama Avenue to 5th/6th
Connection
$800,000
$800,000
$352,000
9
27th Street reconstruction and extension from Yew Avenue
Interchange to Highland Avenue
$3,450,000
$3,450,000
$1,518,000
Subtotal
$5Z406,100
$26,375,000
$26,031,100
$8,746,000
Bikeway Projects
45
Dry Canyon bike path from Highland to Elm Avenue
$336,500
$266,500
$70,000
52
Antler Avenue bike lane construction from 35th to 23rd Street
$70,000
$70,000
$70,000
58
Odem Medo Road bike lane striping
$5,000
$5,000
$5,000
60
South Canal Boulevard bike lane construction from Yew to Heights
Avenue
$130,000
$130,000
$130,000
Subtotal
$541,500
$266,500
$275,000
$205,000
Pedestrian Projects
78
9th Street sidewalk construction of missing links from Highland
Avenue to Canyon Drive
$98,000
$98,000
86
9th Street sidewalk construction from Canyon Drive to Maple Avenue
$125,000
$125,000
76
19th Street/Rimrock Way sidewalk construction from Highland to
Antler Avenue
$145,000
$145,000
80 Black Butte Boulevard sidewalk construction of missing links from $25,000 $25,000
Dry Canyon to North Canal Boulevard
87 Highway 97 sidewalk construction from Jack Pine to Maple Avenue $130,000 $130,000
89 Obsidian Avenue sidewalk construction from Canyon Drive to 15th $70,000 $70,000
Street and 12th Street to South Canal Boulevard
Subtotal $593,000 $130,000 $463,000 $0
Total Phase 1 $53,560,600 $26,781,600 $26,779,100 $8,951,000
Phase 2: 2006 to 2010
Street Projects
7A Maple Avenue connection between North Canal Boulevard and $650,000 $150,000 $500,000 $205,000
Highway 97 (including traffic signal at Highway 97)
D Spruce Avenue construction from 10th Street to Highway 97 $550,000 $550,000 $110,000
21B Alternate Route Planning and Environmental Studies -Part 2
Table 5-1 050101.xis:Funding;jed; 5/2/01 Page I of 4
1W
'EXHIBIT A
TABLE 5-1
Capital Improvement Program
23C Maple Avenue extension from 9th to 19th Street (excluding bridge) $950,000
$950,000 $418,000
8 North Canal Boulevard reconstruction from Antler Avenue to US 97
$1,825,000
$1,825,000
SDC
Reroute
$5,650,000
Total
State/ Total
Eligible
No.
Project
Cost
Federal City
Funding (2)
11
Highland Avenue widening to three lanes between 15th and 27th
$1,775,000
$1,775,000
$90,000
Boulevard
Street
19 Forked Hom Butte Connection
23A
Maple Avenue reconstruction from Highway 97 to 9th Street
$150,000
$150,000
$66,000
23B
Maple Avenue bridge across Dry Canyon (4)
$5,200,000
$5,200,000
$5,200,000
23C Maple Avenue extension from 9th to 19th Street (excluding bridge) $950,000
$950,000 $418,000
8 North Canal Boulevard reconstruction from Antler Avenue to US 97
$1,825,000
$1,825,000
$803,000
Reroute
$5,650,000
$2,486,000
126 to NE 9th
10 Rimrock Way connection to 23rd Street
$475,000
14/15 27th Street extension from Highway 126 (Highland Avenue) to Antler
$475,000
$95,000
H Spruce Avenue construction from Highway 97 to North Canal
$450,000
$450,000
$90,000
Boulevard
19 Forked Hom Butte Connection
Subtotal
$12,025,000
$1,925,000
$10,100,000
$6,987,000
Bikeway Projects
$1,254,000
(including traffic signal at Quartz Avenue and Highway 97)
43 Evergreen Avenue widening for bike lanes from east of RR crossing
$45,000
$45,000
$1,075,000
$215,000
to Jackson Street
$3,575,000
$3,575,000
$1,573,000
Avenue
48 10th Street bike lane construction from Maple Avenue to north UGB
$55,000
$55,000
$55,000
53 Black Butte Boulevard bike lanes striped from Canyon Drive to 5th
$20,000
$20,000
$20,000
Dtre ry Vanyon bike path construction from Quartz to Highland Avenue
55
$160,000
$160,000
Rsidian Avenue bike path construction from 23rd Street to Canyon
56
Drive (4)
$115,000
$115,000
$115,000
57 Obsidian Avenue bike lane striping from Canyon Drive to South
$10,000
$10,000
$10,000
Canal Boulevard
Subtotal
$405,000
$45,000
$360,000
$200,000
Pedestrian Projects
85 Canyon Drive sidewalk construction of missing links from Highland
$335,000
$335,000
Avenue to 9th Street
81 Evergreen Avenue/Ochoco Highway sidewalk construction from east
$60,000
$60,000
of RR crossing to Lake Road
I North Canal Boulevard sidewalk construction from Highland to
$85,000
$85,000
Evergreen Avenue
Subtotal
$480,000
$145,000
$335,000
$0
Total Phase 2
Phase 3: 2011 to
Street Projects
PCs Connect SW 13th Street from Airport Way to Lake Road to Highway
$5,650,000
$5,650,000
$2,486,000
126 to NE 9th
14/15 27th Street extension from Highway 126 (Highland Avenue) to Antler
$1,525,000
$150,000 $1,375,000
$605,000
Avenue (including traffic signal at 27th Street and Highland Avenue)
21C Alternate Route Engineering and Right -of -Way Acquisition
19 Forked Hom Butte Connection
$1,625,000
$1,625,000
$406,250
16/17 Quartz Avenue extension from South Canal Boulevard to Airport Way
$3,000,000
$150,000 $2,850,000
$1,254,000
(including traffic signal at Quartz Avenue and Highway 97)
25B Quartz Avenue improvements from 35th Street to Helmholtz Way
$1,075,000
$1,075,000
$215,000
20 South Canal Boulevard widened to three lanes from Yew to Obsidian
$3,575,000
$3,575,000
$1,573,000
Avenue
Subtotal
$16,450,000
$300,000 $16,150,000
$6,539,250
Bikeway Projects
44 5th/6th Street improvements to add bike lanes and facilitate crossing
65 Antler Avenue shoulder bikeway construction from east of RR
crossing to East 9th Street
$370,000 $370,000
$55,000 $55,000 $55,000
Table 5-1 050101.xis:Funding;jed; 5/2/01 Page 2 of 4
OL
"EXHIBII A
TABLE 5-1
Capital Improvement Program
Pedestrian Projects
96 _, Highway 97 sidewalk construction from Yew Avenue to Odem Medo
$260,000
$260,000
and South Canal Boulevard
SDC
Road
Subtotal
Total State/
Total
Eligible
No.
Project
Cost Federal
City
Funding (2)
66
Evergreen Avenue bike lane striping from 6th Street to Canal
$5,000
$5,000
$5,000
Highway 97 to 4th Street
Boulevard
$205,000
$205,000
Canal Boulevard
67
Fir Street bike path construction across Dry Canyon (3)
$60,000
$60,000
$165,000 $575,000 $0
68
Hemlock Avenue shoulder bikeway construction from east of RR
$60,000
$60,000
$60,000
Total Phase 3
crossing to East 9th Street
$1,110,000
$16,525,000
$6,719,250
70
Kingwood Avenue bike lane construction between Highway 97 and
$60,000
$60,000
$60,000
Straet Projects
North Canal Boulevard
Subtotal
$610,000 $370,000
$240,000
$180,000
Pedestrian Projects
96 _, Highway 97 sidewalk construction from Yew Avenue to Odem Medo
$260,000
$260,000
and South Canal Boulevard
Road
Subtotal
$775,000
$0 $775,000 $775,000
Pedestrian Projects
97 Highway 97 sidewalk construction from Maple Avenue to north UGB
$180,000
$180,000
$145,000
$145,000
98 Kingwood Avenue sidewalk construction from 9th to 8th Street and
$50,000
$225,000
$50,000
$165,000
Highway 97 to 4th Street
99 wckiup Avenue sidewalk construction from 34th Street to South
$205,000
$205,000
Canal Boulevard
91 Salmon Avenue sidewalk construction from 1 st Street to Airport Way
$85,000
Subtotal
$85,000
$165,000 $575,000 $0
Subtotal
$575,000
$440,000
$135,000
$0
Total Phase 3
$17,635,000
$1,110,000
$16,525,000
$6,719,250
Phase 4: 2016 to 2020
Straet Projects
22 15th Street improvements from Quartz to Obsidian Avenue
$325,000
$325,000
$65,000
24 27th Street extension from Antler to Maple Avenue
$2,800,000
$2,800,000
$1,232,000
21D Alternate Route Construction
18 East 9th Street improvements from Highway 126 to Maple Avenue
$3,700,000
$3,700,000
$1,628,000
713 Maple Avenue reconstruction from east of RR crossing to UGB
$675,000
$675,000
$0
PC6 Connection of NW 19th Street to NW Spruce (portion within the UGB)
$800,000
$800,000
$160,000
PC7 SW Salmon Ave & Odem Medo Connector Project - S. Canal Blvd to
$952,300
$952,300
$190,460
19th St.
Subtotal
$9,252,300
$0
$9,252,300
$3,275,460
Bikeway Projects
64 35th Street shoulder bikeway construction from Antler to Hemlock
$75,000
$75,000
$75,000
Avenue
69 Hemlock Avenue shoulder bikeway construction from 35th to 19th
$155,000
$155,000
$155,000
Street
72 North Canal Boulevard bike lane construction from US 97 Reroute to
$240,000
$240,000
$240,000
north UGB
75 Wickiup/Reservoir Road shoulder bikeway between Helmholtz Way
$305,000
$305,000 $305,000
and South Canal Boulevard
Subtotal
$775,000
$0 $775,000 $775,000
Pedestrian Projects
$150,000
$150,000
84 15th Street sidewalk construction from Obsidian to Highland Avenue
$145,000
$145,000
95 Canyon Drive sidewalk construction from Quartz to Highland Avenue
$225,000
$225,000
82 Highway 126 from East 9th Street to Sisters Avenue
$165,000
$165,000
99 wckiup Avenue sidewalk construction from 34th Street to South
$205,000
$205,000
Canal Boulevard
Subtotal
$740,000
$165,000 $575,000 $0
Phase 4
When Warranted
Street Projects
29 Traffic Signal at Black Butte Boulevard and 5th Street (Highway 97)
$150,000
$150,000
26 Traffic Signal at Kingwood Avenue and Highway 97
$150,000
$150,000
27 Traffic Signal at Canyon Drive and Highway 126
$160,000
$150,000
28 Traffic Signal at Sisters Avenue and Highway 126
$150,000
$150,000
Table 5-1050 10 I.x1s:Fundingjed; 5/2/01 Page 3 of 4
EXHIBIT 'A
TABLE 5-1
Capital Improvement Program
Notes,
(1) Roadway classification corresponds to Redmond's map of existing and future transportation facilities that was adopted in 1998.
(2) Eligibility for SDCs was estimated as the proportion of the improvement which provides capacity over a local roadway. For minor arterial, major collector, and industrial
collector projects, this includes both added roadway capacity and bike lanes. For minor collector projects, this only includes added roadway capacity. Sidewalks were not
considered SDC eligible since they are part of the local roadway standard. To calculate SDC eligible costs, local roadway construction costs were estimated to be 56% of a
minor arterial, 80% of a major collector, 75% of a minor collector, and 71% of an industrial collector.
(3) Bike path projects have been identified in the transportation element of the Public Facilities Plan. Most are not SDC eligible since they are principally for recreational uses
and not capacity enhancements. However, they may be eligible for parks SDCs.
(4) This project is 100% SDC eligible since the entire improvement will add capacity to the transportation system. The extension will provide an east -west connection with ne
local access.
(4) The bike path connecting Obsidian Avenue through Dry Canyon has been included as a transportation SDC eligible project since it is a capacity enhancement allowing
bicyclists to continue along a roadway and is not primarily a recreational path.
Table 5-1 050101.xls:Funding;jed; 512/01 Page 4 of 4
SDC
Total
State/
Total
Eligible
No. Project
Cost
Federal
City
Funding (2)
30 Traffic Signal at East 9th Street and Highway 126
$150,000
$150,000
31 Traffic Signal at Obsidian Avenue and South Canal Boulevard
$150,000
$150,000
$150,000
32 Traffic Signal at Quartz Avenue and South Canal Boulevard
$150,000
$150,000
$150,000
33 Traffic Signal at Salmon Avenue and South Canal Boulevard
$150,000
$150,000
$150,000
34 Traffic Signal at Yew Avenue and South Canal Boulevard
$150,000
$150,000
$150,000
35 Traffic Signal at Odem Medo Road and South Canal Boulevard
$150,000
$150,000
$150,000
38A Traffic Signal at 19th Street and Antler Avenue
$150,000
$150,000
$150,000
37 Capacity improvements at 19th Street and Hemlock Avenue
$30,000
$30,000
$30,000
38 Capacity improvements at 19th Street and Antler Avenue
$30,000
$30,000
$30,000
40 Capacity improvements at 9th/10th Street and Maple Avenue
$30,000
$30,000
$30,000
41 Capacity improvements at 19th Street and Maple Avenue
$30,000
$30,000
$30,000
Subtotal
$1,770,000
$750,000
$1,020,000
$1,020,000
Subtotal Phase 1
$53,560,600
$26,781,500
$26,779,100
$8,951,000
Subtotal Phase 2
$12,910,000
$2,115,000
$10,795,000
$7,187,000
Subtotal Phase 3
$17,635,000
$1,110,000
$16,525,000
$6,719,250
Subtotal Phase 4
$10,767,300
$165,000
$10,602,300
$4,050,460
Subtotal When Warranted
$1,770,000
$760,000
$1,020,000
$1,020,000
TOTAL - All Projects
$96,642,900
$30,921,500
$65,721,400
$27,927,710
Notes,
(1) Roadway classification corresponds to Redmond's map of existing and future transportation facilities that was adopted in 1998.
(2) Eligibility for SDCs was estimated as the proportion of the improvement which provides capacity over a local roadway. For minor arterial, major collector, and industrial
collector projects, this includes both added roadway capacity and bike lanes. For minor collector projects, this only includes added roadway capacity. Sidewalks were not
considered SDC eligible since they are part of the local roadway standard. To calculate SDC eligible costs, local roadway construction costs were estimated to be 56% of a
minor arterial, 80% of a major collector, 75% of a minor collector, and 71% of an industrial collector.
(3) Bike path projects have been identified in the transportation element of the Public Facilities Plan. Most are not SDC eligible since they are principally for recreational uses
and not capacity enhancements. However, they may be eligible for parks SDCs.
(4) This project is 100% SDC eligible since the entire improvement will add capacity to the transportation system. The extension will provide an east -west connection with ne
local access.
(4) The bike path connecting Obsidian Avenue through Dry Canyon has been included as a transportation SDC eligible project since it is a capacity enhancement allowing
bicyclists to continue along a roadway and is not primarily a recreational path.
Table 5-1 050101.xls:Funding;jed; 512/01 Page 4 of 4
EXHIBIT A
TABLE 5-113
City of Redmond
Transportation System SDC Schedule
SDC per PM peak hour trip
$27,927,710 (cost basis) / 15,172 (projected number of PM peak hour trips generated by
new development, 1998-2020) = $1,841 (cost per trip)
1999 SDC 2001 SDC
$1,841 $1,905
The 2001 SDC is based on ENR Index of 6076 in July 1999 and 6286 in April 2001. 6286/6076=1.0346
2001 SDC of $1,905 = $1,841 X 1.0346
The 1999 SDC of $1,841 has been revised from previous information due to updates in the
Transportation System CIP
o:\chmx0025\SDC update tables.xls
512101
r.
w
m
N
°E
O
N
O
00
N
O
01
w
C
°
fOA
N
44
44
y
m
O
M
G
g
O
O
O
O
O
O
O
O
9
o
Cl
0
0
U
a to
�
r
!9
a
a
A
U
�4
$
N
g
Co
O
°
H
coMM
In
NN
N
Vs
N
40%
40
40
m
C
n
O
N
O
C
O
O
O
O
1D
w
M
v,
MO
to►
0
d
c
O
o
O
N
O
h
V
M
`ffs
r-
O
Q
�
w
{Cp
co
t --:N
W
•Y�
i
Q
O
O
a
�
�i
ago
0
0
40
0)
r
of
&6
6
o
g to
ri
m
Ti
m
t
t3
m
2"i in
m W !u
�' w
o A�
o
Q u K
d
Yl
O
w �i
N
D
�i
a
E
a
a
a
a
a c¢
cQ
a!
a 'S Q'
CC 0
u
•-
�a
a
0
0
c
0
0
m
0 0'�'
hcb
o'°
o m E
ea
Q
a!)
m
e4D
a
Q
c
�'t3
=)
E
z
z
z
z
z
z
CL
a
Q
Q
a
>
m
Ua
SW?
N-Ef
N
0
co r-
a
0
V)
°
z
m
m
m
cc
m 00
m
C
a E eo
��
� a
c
c
°
c
°
a
a
a
a
E
a a
o�
a
E
a >v
o �1
CL
..
N
f
f
f
f
f E w
f
fm
a �°
s
aL
c
g,�
t �
.
.� a
uS
m
a
z
z
z
z
z °'°
z
z
z
Lb
lb
d
_
OL. Z
r
r
r
N N
N
N
co
N
M
r.
w
m
N
N
J
C
N
E
a�
2
Ia.
E
3§
o V
4
a
N
E
1= N
C
V
�
^
N N (OA
00
O
O
V
N
N
Go
co
C
fA
4
�
4A
N
t-
O
C14
Go
to
N
O
C d
c6
c6
c6
ad
c6
c6
p6
p6
�
a
a
O
0
0
O
0
0
0
(�
0
0
0
0
0
0
0
0
0
t
co0
H
to
M
O
M
M
b9
E
E
O
0
O
0
O
0
O
0
O
0
0
O
0
O
0
N An
M
O
i!
m
OD
Nf
fA
.�--
Vi
cm
M
�gn
N
i
0
O
M
M
c
Q
u
a
a'
f-
0
0
(`�
n
(00
0
aY
(O
N
M
O
M
C3
A
d
O1
Cl_
yca
ym
L Q
H U
0=
420
Q=
Q
Q
'0
C
V
T
cc
a
O
Oi
C
O
W
H
C
0
y
C
O)
C
V
"E
(�00
E
ac
2
do
m
E
o
u
m
c>
n o
>
E
o o
6, E
_m
n t-
n
n co
CL
CL
°=
n
U�
>>
Eacc
c
t
Ern_
Ems,
Ern_
z
ID
E
(x
of-
c
�..
�`�
�.,
Q
� a
o�
Q
UE
U
CO
u
'
m
m
a��i
I
cc
ca
4�
_
csi
C
�
w
a
CL
L
OU-
j5
CL
L
L N
'�
N
O
>.
U
a
U-
Lcc
C
L
U.
U.
c
lL
U-
LLL y
11 y
lL
2
lL
15U E
N
Ca
CL
m c
a.r
(Caam
CLE
Md
ad
m m
a°g' a=
(a
a
(haw
aM
mw
aM
m
a
(a
CL
my
n.o
�a
_��
o
m�'
V
Em
�
a
u'S N
I
Lb
Lbu'S
u'S
u'S �
u'S �
uS �
� a
�
2
2
Z
Z
Z
2
Z
�pZ
�.
Q
U
0
m
U
U
z M
M
MM
M
M
M
OUp
M
M
V
NV
2
4
N
d
R
J
N
J
C
N
0
a
3§
U
co
a-
0 O
�L
Z
c4
O
�V
p C
4)
'D E
w Q
ea o
E d
W 0
E
S
8
o
C
w
4
w
w
c
G
N
K
N
1
M
O
A
w
M
0
0
0
o
c
0
0
coo
0
co
o
�
a
a
A
U
io
o0
0
0
0
0
0
0
0
0
o
0
a
0+
~
^
Ne�
M
N
4n
in
to
N
N
N
w
c
O
C
o
O
O
O
o
O
0
O
o
O
Cl
O
n
M
N
NN0
N
°ifA
i
w
c
o
�
:.
N
to
v
7
cr
V
�
N
Q
�
0
in
O
N
O
Cl1-
O
QN
('i
1l7
1�
Y7
M
N
a
o
vm
:2 ca
c
30
§0
coo
Q
Qa
0=
O
ot`,
_
co
c
o
m
m
m
� �
�
c
m�
o
o
c
0
C
drn
dt�`a
c
0.. 0
�
�
W 2
C
iii
o
E0
Ea
„
�
�
ri
c
�-
AI
I
�v
`—°�
�Eu�=
zip
"'U
a
,o
o
=
m
E'0
-C
wo
CL
v_
c
a
,
�v
cn
CO
C
t X
= a
r
d
5
—
a
v
m o
m
o
�a
~
o
LLU
v
c0a
LL�
coa
y
>
c
A
,� �
ca
O
mU
F
a
LL8
a
c
o.
ma
��
mo
b
m
o
z U.15m
1•0
0-
H
p
d
a`
CO
3
Z
Z
d
0
aZp
Q
z
z
z
z
z
z
U
MMUp
Z V
�p�p
a
st
p
1n
b
Z
c4
O
�V
p C
4)
'D E
w Q
ea o
E d
W 0
L
O
Z
C
w
C
8c
N
N d
C N �
p C E9
d co
C
Cl. N
v N to
Co r.3
N
> d' O
ocv
Ema�
$EE
cc8v
o mw
U
y C
>.
U r C
QQU
N M
N
N
aQ�
O Q
O O �
O O O
vjOO
f -0C
�rfb
O
O O O
O O O
6 O O
M 6n U')
,r- to U)
619 69 69
EXHIBIT D
TABLE 8 4B
City of Redmond
Parks SDC Schedule
SDC per residential household
$4,201,913 (cost basis) / 20,645 (population growth in people) _ $203.53 (cost per capita)
$203.53 (cost per capita) X 2.24 (persons pe household) _ $456 (cost per household)
1999 SDC 2001 SDC
$456 $458
The 2001 SDC is based on ENR Index of 6259 in October 2000 and 6286 in April 2001. 6286/62596=1.0043
2001 SDC of $458 = $456 X 1.0043
o:\chmx0025\SDC update tables.xls
5/2/01