Loading...
15-268-Order Recorded 1/12/1972In the Matter ) of ) IN THE BOARD OF COUNTY COMMISSIONERS OF Ti(E STATE OF OREGON FOR THE COUNTY OF DESCHUTES O R D E R VOL O• -DE -58H t5 PAGF 268 A permit is granted by Deschutes County to Pacific Gas Transmission Co. t0 install a 36" steel pipeline on or across Deschutes County right-of-way. A detailed description and map of this operation must be provided on the reverse side of this sheet. This permit is subject to the following gen- eral specifications and is revocable at any time upon written notice by the Deschutes County Board of Commissioners. GENERAL SPECIFICATIONS FOR PARTICULAR IlSTALLAT104S Installing Pike Line Parallel: All pipe lines running parallel with the road shall be in the existing ditch line, or no less than three (3) feet from the edge of the existing pavement edge. All pipe lines must be installed to a depth to be no less than two (2) feet and properly backfilled to the original grade line and with no obstructions to the drainage area. Permittee shall be responsible for any or all damages to the existing pavement, and shoulders or other objects or areas within the right-of-way. Installing Pipe line Transverse: All pipe line installations laid transversely to the road bed or right-of-way shall be installed in the following manner: All pavement cuts prior to the excavation shall be made with a breaking harmer so as to insure neat finish cut lines. All pipe lines shall be installed to a depth of no less than two (2) feet below the existing road- side ditch elevation. In all cases where a ;Mater line is installed inVa trans-' verse direction the water pipe must be installed 00hin a larger pipe which size shall be no less than six (6) inches in diameter. Backfilling and Paving: The permittee shall*be required to properly backfill the trench in such a manner as to guarantee a well compacted, stab biized sub -base prior to paving- The pave- ment must be replaced to its original line, crown, and grade with an asphalt mixture to conform with the surrounding road bed. The area of installation must be kept smooth for the.traveling public at all times. The permittee will be required at all times to take every precaution to protect the traveling public.. All signs and traffic controls shall be furnished by the permittee. In regard to other utility installations, such.as gas lines, telephone lines and . electric conduits, all the general specifications shall apple if they are to be run under ground, frith one exception: It would not be necessary to have these lines within a larger pipe when crossing the right-of-way. Dated this--� — -day of e 19/ - Rely m vended l;ppro al Charles L. Plummer, DESCHUTES COUNTY ROADMASTEP, PE4M 'T TEE Pacific Gas Transmission Company