9-184-Order Recorded 8/5/1964\VaL m 184
IN THE COUNTY COURT OF THE STATE OF OREGON
FOR THE COUNTY OF DESCHUTES
In the Matter August 12, 1964
)
of ) ORDER
Installing Water Lino )
A permit is granted by Deschutes County to W.E. ROata
to install 21' water line on or across Deschutes County right-of-way. A de-
tailed description and map of this operation must be provided on the reverse side of
this sheet. This permit is subject to the following general specifications and is
revocable at any time upon written notice by the Deschutes County Gourt.
GENERAL SPECIFICATIONS FOR PARTICULAR INSTALLATIONS
7rsta11i.n Pipe : Line Urallelt +2" water litre All pipe lines running
parallel with the road shall be in the existing ditch line, or no less than three
(3) feet from the edge of the existing pavement edge. All pipe lines must be in-
stalled to a depth to be no less than two (2) feet and properly backfilled to the
original grade line and with absibnbi7toitiehot6lith4i'rdtaigage area. Permittee shall
be responsible for any or all damages to the existing pavement, and shoulders or
other objects or areas within the right-of-way.
IrStallinF Pipe Line Transverse: 2" water line All pipe line installations
laid transversely to the road bed or right-of-way shall be installed in the following
manner: all pavement cuts prior to excavation shall be madb.r_fdltli ir_btbaking hammer
sus as tc insure neat finish cut lines. All pipe lines shall be installed to a depth
of no less than two (2) feet below the existing roadside ditch elevation. In all
cases where a water line is installed in a transverse direction the water pipe must
be installed within a larger pipe which size shall be no less than six (6) inches in
diameter. Backfilling and Paving: The permittee shall be required to properly back-
fill the trench in such a manner as to guarantee a well compacted, stabilized sub-
base prier to paving. The pavement must be replaced to its original line, crown,
and grade with an asphalt mixture to conform with the surrounding road bed. The
area -)f installation must be kept smooth for the traveling public at all times. The
permittee will be required at all times tc take every precaution to protect the
traveling public. All signs and traffic controls shall be furnished by the permit-
tee.
In regard to other utility installations, such as gas lines, telephone lines, and
electric conduits, all the general specifications shall apply if they are t4 be run
under ground, with one exception: It would not be necessary to have these lines
within a larger pipe when crossing the right-of-way.
R nded Apprrva
C~iar es L. Plummer, Roadmaster
DESCHUTES COUNTY
Approved County Court:
COUNTY JUDGE
COUNTY COMMISSIONER
COUNTY COlaviISSIONER
FERNIITTEE
r x.