HomeMy WebLinkAboutDoc 091 - Temp Construction Easement - SkylinersDeschutes County Board of Commissioners
1300 NW Wall St., Suite 200, Bend, OR 97701-1960
(541) 388-6570 -Fax (541) 385-3202 -www.deschutes.org
AGENDA REQUEST & STAFF REPORT
For Board Business Meeting of March 6, 2013
DATE: February 26,2013
FROM: George Kolb, County Engineer Road 541-322-7113
TITLE OF AGENDA ITEM:
Consideration of Board signature of Document No. 2013-091, an Acceptance Deed for a Temporary
Construction Easement on Skyliners Road from 61579 Boulder LLC
PUBLIC HEARING ON THIS DATE? NO.
BACKGROUND AND POLICY IMPLICATIONS:
Deschutes County is working with the Federal Highway Administration (FHW A) to reconstruct
Skyliners Road. The reconstruction of Skyliners Road will involve widening the existing road out to a
width of 34 feet to include six-foot bike lanes the entire length ofthe project. Because of this widening,
the grade on several private residence driveways will be affected to the point that the contractor will be
required to enter onto private property in order to reconstruct the driveway to an acceptable grade.
FHWA requires a construction easement from the individual property owners allowing the contractor
onto their private property to accomplish the work. These easements will be in effect until the
completion of the road project at which point they will no longer be in effect. On August 22, 2012, the
Board of County Commissioners signed Resolution No. 2012-104, approving the acquisition ofthese
temporary construction easements for the Skyliners Road Project.
FISCAL IMPLICATIONS:
The amount $542.85 required for this Temporary Construction Easement is budgeted in FY 2012-2013.
RECOMMENDATION & ACTION REQUESTED:
Move approval of Board signature of Document No. 2013-091, accepting the Temporary Construction
Easement from 61579 Boulder LLC
ATTENDANCE: George Kolb, County Engineer
DISTRIBUTION OF DOCUMENTS:
Copy to Sheila Odie (ext. 7148) at the Road Department after recording
DESCHUTES COUNTY DOCUMENT SUMMARY
(NOTE: This form is required to be submitted with ALL contracts and other agreements, regardless of whether the document is to be
on a Board agenda or can be signed by the County Administrator or Department Director. If the document is to be on a Board
agenda, the Agenda Request Form is also required. If this form is not included with the document, the document will be returned to
the Department. Please submit documents to the Board Secretary for tracking purposes, and not directly to Legal Counsel, the
County Administrator or the Commissioners. In addition to submitting this form with your documents, please submit this form
electronically to the Board Secretary.)
Please complete aU sections above the Official Review line.
Date: IFebruary 26, 20131 Department: IRoadl
Contractor/Supplier/Consultant Name: ~1579 Boulder LLCI
Contractor Contact: [erry Skjersaal Contractor Phone #: 1541-410j
11426
Type of Document: Acceptance Deed for a Temporary Construction Easement on
Skyliners Road from 61579 Boulder LLC.
Goods and/or Services: Temporary Construction Easement
Background & History: Deschutes County is working with the Federal Highway
Administration (FHWA) to reconstruct Skyliners Road. The reconstruction of Skyliners
Road will involve widening the existing road out to a width of 34 feet to include six foot
bike lanes the entire length of the project. As a result of this widening, the grade on
several private residence driveways will be affected to the point that the contractor will
be required to enter onto private property in order to reconstruct the driveway to an
acceptable grade. FHWA requires a construction easement from the individual property
owners allowing the contractor onto their private property to accomplish the work.
These easements will be in effect until the completion of the road project at which point
they will no longer be in effect. On August 22,2012, the Board of County
Commissioners signed Resolution No. 2012-104, approving the acquisition of these
temporary construction easements for the Skyliners Road Project.
Agreement Starting Date: IUpon Signatur~ Ending Date: lEnd of
IProjec~
Annual Value or Total Payment: 1$542.851
D Insurance Certificate Receiied (CieCk box)
Insurance Expiration Date:
Check all that apply:
RFP, Solicitation or Bid Process
Informal quotes «$150K)
Exempt from RFP, Solicitation or Bid Process (specify -see DCC §2.37)
Funding Source: (Included in current budget? l2J Yes D No
If No, has budget amendment been submitted? Yes D No
2/26/2013
Is this a Grant Agreement providing revenue to the County? 0 Yes [g] No
Special conditions attached to this grant:
Deadlines for reporting to the grantor:
If a new FTE will be hired with grant funds, confirm that Personnel has been notified that
it is a grant-funded position so that this will be noted in the offer letter: 0 Yes 0 No
Contact information for the person responsible for grant compliance: Name:
Phone #:
Departmental Contact and Title: George Kolb, County Engineer
Phone #: 541-322-7113
Department Director Approval: ---'c::.G,l--s~."""""=~""":=---1IL.¥.i"-'tIL----Ign~
Distribution of Document: Who gets the original document and/or copies after it has
been signed? Include complete information if the document is to be mailed.
Official Review:
County Signature Required (check one): 0 BOCC Department Director (if <$25K)
Administrator (if >$25K but <$150K; if >$150K, BOCC Order No. _____.)
Legal Review Date
Document Number ___________
2/26/2013
For Recording Stamp Only
After recording return to:
Deschutes County Road Dept.
61150 S.E. 27th Street
Bend, Oregon 97701
TEMPORARY CONSTRUCTION EASEMENT
61579 Boulder LLC ,Grantor, does hereby grant to Deschutes County, Oregon, Grantee,
its successors and assigns, a Temporary Construction Easement for construction purposes,
over and across the Grantor's property as described in Exhibit "An, attached hereto and by
this reference incorporated herein.
The true consideration for this conveyance is $542.85 and other good and valuable
consideration, the receipt and sufficiency of which are hereby acknowledged.
The Grantee's use of the easement shall include the right for the Grantee, its employees,
agents, assigns, contractors and employees of contractors to enter and use the easement 1
area for construction work in connection with the Skyliners Road Reconstruction project.
The term and duration of this temporary construction easement shall be from Api! 1, 2013 to
the completion of the Skyliners Road Reconstruction project.
This document is intended to grant easements on the property described, not to convey fee
title or any interest in the underlying property except as expressly stated herein. The
easements granted shall not prevent Grantors from the use of said property provided,
however, that such use shall not be permitted to interfere with the rights herein granted.
Grantor shall not be permitted to endanger the lateral support of any facilities constructed
within or adjacent to the easements granted herein.
Grantor agrees that the consideration recited herein is just compensation for the property or
property rights conveyed, including any and all damages to Grantor's remaining property, if
any, which may result from the acquisition or use of said property and the construction or
improvement in the public way.
Grantor(s) hereby covenant(s) to and with Grantee that itltheyis/are the owner of said
property, which is free from all encumbrances, except for easements, conditions and
PAGE 1 OF 3 -CONSTRUCTION EASEMENT AND ACCEPTANCE
restrictions of record, and will warrant and defend the easement rights herein granted from all
lawfull claims whatsoever, except as stated herein.
~
IN WITNESS WHEREOF, this document is executed this % -day of
__,..-:-....;~-==--("_u_q_-I-____• 2013.
By: ~_~=-~~____________
STATE OF OREGON )
) 88.
County of Deschutes )
This instrument was acknowledged before me byTerry 8kjersaa as Member of 61579
Boulder LLC.
Dated this ;.J-day of
EGON
My Commission Expires: <6 ~ ;1.;t. -J'-I
NOTARY PUBLIC FOR
PAGE 2 OF 3-CONSTRUCTION EASEMENT AND ACCEPTANCE
EXHIBIT A
Tax lot 18·1O-10AA 2300
A tract of land lying in the NEY4 of Section 10, Township 18 South, Range 10 East, W.M., Deschutes
County, Oregon and being a portion of Lot 1, Block A. Skyliner Subdivision and being more particularly
described as follows:
Commencing at the ~inch diameter rebar monumenting the southwesterly corner of Lot 3, Block A of
Skyline Subdivision; thence along the northerly right-of-way line Skyliners Road N56°14'27"E a
distance of 239.23 feet to the % inch diameter iron pipe monumenting lhe southeasterly corner of said
Lot 1. Block A. Skyline Subdivision; thence leaving said Skyliners right-of-way line and along the
easterly line of said Lot 1 (being the westerly right-of-way line of Boulder Road) NOO"28'54"E a
distance of 80.30 feet to the Point of Beginning; thence NOO"28'54"E a distance of 36.61 feet;
thence leaving said easterly lot line N67"44'36'W a distance of 11.40 feet; thence S22"15'24"W a
distance of 34.00 feet; thence S67°44'36"E a distance of 24.98 feet to the Point of Beginning.
Bearings are grid bearings based on the Deschutes County Surveyor's Office Central Oregon
Coordinate System.
Containing 618 square feet (0.01 acres) more or less.
This tract is depicted on the attached map titled "Exhibit "An Sketch" which is incorporated herein by this
reference.
f
I
I
\
J:\CAD\Projecls\RD3S3S·Skyliners\Oeeds\Skyliner-181010AA02300·61579 BOUlOER-lgl.doc)( Page 1 of 1
7/27/2012
\
\
\
\
\
SCALE:
\
\
\
3
\
\
\
1" = 50'
\ 2
\
\
\
\
\ ,...~\ -.0,,~
",4>
Vol-Page: 2006-73565
DATE: 7/27/2012
181010 AA 02300
61579 BOULDER LlC
16396 SKYliNE DR
BEND OR 97701
Site Address: 61579
BOULDER RD
BEND 97701
SKYLINE SUBDIVISION Lot:
d··.mJi..!h...."" ..I···i!"..'''''sb''JI'''··..,·,"il..,'wFpil''·''';bo PT 1.2 Block: A
ACCEPTANCE
Deschutes County, acting by and through its Board of County Commissioners, does hereby
accept the foregoing Temporary Construction Easement.
DATED this __day of ____________, 2013.
BOARD OF COUNTY COMMISSIONERS
OF DESCHUTES COUNTY, OREGON
ALAN UNGER, CHAIR
ATrEST:
TAMMY BANEY, VICE CHAIR
Recording Secretary
ANTHONY DEBONE, COMMISSIONER
STATE OF OREGON )
) SS.
County of Deschutes )
Before me, a Notary Public, personally appeared Alan Unger, Tammy Baney, and
Anthony DeBone, the above-named Board of County Commissioners of Deschutes County,
Oregon, acknowledged the foregoing instrument, on behalf of Deschutes County, Oregon.
Dated this __day of _________, 2013.
NOTARY PUBLIC FOR OREGON
My Commission Expires: _____
PAGE 3 OF 3 -CONSTRUCTION EASEMENT AND ACCEPTANCE