AGENDA REQUEST & STAFF REPORT
For Board Business Meeting of January 28, 2015
Please see directions for completing this document on the next page.
DATE: January 15,2015
FROM: George Kolb, County Engineer Road 541-322-7113
TITLE OF AGENDA ITEM:
Consideration of Signature of Document No. 2015-052, A Funds Transfer Agreement between
Deschutes County and the Federal Highway Administration for the Payment of Deschutes County's
Share of the Project Costs for the Fall Creek Bridge Replacement project.
PUBLIC HEARING ON THIS DATE? NO
BACKGROUND AND POLICY IMPLICATIONS:
Deschutes County is working with the Federal Highway Administration, Western Federal Lands
Highway Division (FHWA) on the replacement of the Fall Creek Bridge located on Cascade Lakes I
Highway. On August 28,2013, the County signed a Federal Lands Access Program Match Agreement "
for the Fall Creek Bridge Replacement project with a subsequent modification to the agreement signed
on January 13,2015. As part ofthis agreement, the County was obligated to provide a 10.27% match of J_••
the project costs. The County's share of the project cost is $224,480. The Funds Transfer Agreement i
provides the necessary information for the fund transfer to proceed and has to be signed before payment
can be made by Deschutes County. There are two originals that will need to be signed for future
distribution to the FHW A and Deschutes County
FISCAL IMPLICATIONS:
The amount of$284,500 is budgeted in the FY 14 -15 FY
RECOMMENDATION & ACTION REQUESTED:
After review of the information with the BOCC, move Board signature of Document No. 2015-052,
Funds Transfer Agreement between Deschutes County and the Federal Highway Administration for the
Payment of Deschutes County's Share of the Project Costs for the Fall Creek Bridge Replacement
project.
ATTENDANCE: George Kolb, County Engineer
DISTRIBUTION OF DOCUMENTS:
Return both signed originals to Sheila OdIe (ext. 7148) at the Road Department for further distribution
to the FHWA.
DESCHUTES COUNTY DOCUMENT SUMMARY
(NOTE: This form is required to be submitted with ALL contracts and other agreements, regardless of whether the document is to be
on a Board agenda or can be signed by the County Administrator or Department Director. If the document is to be on a Board
agenda, the Agenda Request Form is also required. If this form is not included with the document, the document will be returned to
the Department. Please submit documents to the Board Secretary for tracking purposes, and not directly to Legal Counsel, the
County Administrator or the Commissioners. In addition to submitting this form with your documents. please submit this form
electronically to the Board Secretary.)
Please complete all sections above the Official Review line.
Date: Qanuary 15, 20151 Department: IRoadl
Contractor/Supplier/Consultant Name: IFederal Highway Administrationl
Contractor Contact: INancie Pruiij Contractor Phone #: 1360-619j
~6721
Type of Document: Funds Transfer Agreement
Goods and/or Services: Outlines responsiblities of the Federal Highway Adminstration
and Deschutes County concerning the transfer of funds for the Fall Creek Bridge
Replacement project.
Background &History: Deschutes County is working with the Federal Highway
Administration, Western Federal Lands Highway Division (FHWA) on the replacement
of the Fall Creek Bridge located on Cascade Lakes Highway. On August 28, 2013, the
County signed a Federal Lands Access Program Match Agreement for the Fall Creek
Bridge Replacement project with a subsequent modification to the agreement signed on
January 13, 2015. As part of this agreement, the County was obligated to provide a
10.27% match of the project costs. The County's share of the project cost is $224,480. I
The Funds Transfer Agreement provides the necessary information for the fund transfer
to proceed and has to be signed before payment can be made by Deschutes County.
There are two originals that will need to be signed for future distribution to the FHWA
and Deschutes County
Agreement Starting Date: lupon signature! Ending Date: 112/31/2016
Annual Value or Total Payment: 1$224,48Q
I
D Insurance Certificate Receiied (CleCk box)
Insurance Expiration Date:
Check all that apply:
D RFP, Solicitation or Bid Process
D Informal quotes «$150K)
D Exempt from RFP, Solicitation or Bid Process (specify -see DCC §2.37)
Funding Source: (Included in current budget? [8] Yes D No
If No, has budget amendment been submitted? DYes D No
1115/2015
Is this a Grant Agreement providing revenue to the County? DYes I2?J No
Special conditions attached to this grant:
Deadlines for reporting to the grantor:
If a new FTE will be hired with grant funds, confirm that Personnel has been notified that
it is a grant-funded position so that this will be noted in the offer letter: DYes D No
Contact information for the person responsible for grant compliance: Name:
Phone#:
Departmental Contact and Title:
Phone #: 541-322-7113 l
Department Director Approval: _~:..-
, Da
__--:;..._____
Signature I
Distribution of Document: Who gets the original document and/or copies after it has i
been signed? Include complete information if the document is to be mailed.
Official Review:
County Signature Required (check one): 0 BOCC 0 Department Director (if <$25K)
o Administrator (if >$25K but <$150K; if >$150K, BOCC Order No. ____-I) l
Legal Review
Document Number __________________
JDate
t:
I
f
i
I
t•f
,
I
I
1115/2015
Fall Creek Bridge Replacement
2013 Oregon Federal Lands Access Program
Project Location
I
2,000
I
3,000
I
4,000 Feet
Print: November 14, 2012
Legend
) ( Bridge
I Milepost
Fall Creek Bridge
--County Road
---Stream
Lake
The informaliClll on this mepWIJS deriwd fran dpl databases on
Descltutes CounCy's G.I.S . C_ was IIIIl1en in !he creation ofthis
map, but it is prQ\lided "as is". ()eschules County cannot accept any
responsilMty for errors, orrissi«lS, or positional accuracy in II1e clgital
data Of" the underlying records . ThenI are no w.l1IhIies, I!XprHS or
implied, inc:ludng the warranty of merchlllltallilily or fttness !Dr II
particular pu~lICCornponying It\is prodJd. Ho_, notilclllion
of eny erron> win be aW"eciated.
P :lArcGIS_ProjectsI BridgesI FalJ Creek Bridge Replacement
REVIEVv/ED
rEGA! CO! 1blS!L_,___
us Department ofTransportation Western Federal Lands Highway Division
Federal Hilhway Administration 610 E. Fifth Street .
Vancouver,VVA 98661
Funds Transfer Agreement
Wednesday, January 14, 2015
Deschutes County
Providing Funding of $224,480
Western Federal Lands Highway Division, FHWA Agreement II DTFH70-15-E-OOOO8
Project Number/Name: OR PFH 46(13), Fall Creek Bridge Replacement
This letter is to confirm that Deschutes County has committed to provide through either electronic funds' transfer or by
check, $224,480 to the Western Federal Lands Highway Division, FHWA for project work and/or a construction contract to
eliminate load limits and debris accumulation on the Fall Creek Bridge on the Cascade Lakes Highway at MP 26.52.
Fund Transfer Summary:
Phase Form Amount Received FTANumber Amend II Comment
I CN Cash $224,480 DTFH7015EOO008 Match for CN, CE, CM.1
I Total: $224,480
I The following is the Deschutes County's Finance Billing The following is Western Federal Lands Highway
Information: Division, FHWA Finance Billing Information:
DUNS#
Tax 10 II
030-805-147
93-6002292
DUNS#
Tax ID#
139-768-597
22-3934584
Finance Contact Wayne Lowry
Finance Phone (541) 617-4721
Finance Fax
Finance E-mail
Street Address
City, State, Zip
finance@deschutes,ors;
61150 SE 27th Street (Road
1300 NW Wall Street. 2nd Floor
Bend,OR 97702
Project Contact George Kolb
Project Contact Phone (541) 322-7113
Project Contact Fax
Project Contact E-mail finance@deschutes.o!S
Finance Contact
Finance Phone
Finance Fax
Finance E-mail
Genise L Dance
(360)'619-7534
(360) 619-7945
. genise.dance@dot.gov
Pete Field Project Contact
Project Contact Phone (360) 619-7619
Project Contact Fax (360) 619-7945
Project Contact E-mail peter.field@dot.gov
Expiration Date: This Funds Transfer Agreement will expire on December 31, 2016.
The current authorized funding is $224,480.00. In no case shall the Deschutes County or FHWA exceed this amount or extend
the end date of the agreement without a mutually agreed upon written modification of this Agreement.
Anthony DeBone, Deschutes County Commissioner
Deschutes County, Oregon
Date Marlene M. Marcellay, Contracting Officer
Western Federal Lands Highway Division, FHWA
Date
I
I
f ~
!
DC 201 - 0 5?