HomeMy WebLinkAboutRelease - Tetherow Performance BondDeschutes County Board of Commissioners
1300 NW Wall St., Suite 200, Bend, OR 97701-1960
(541) 388-6570 - Fax (541) 385-3202 - www.deschutes.org
AGENDA REQUEST & STAFF REPORT
For Board Business Meeting of Monday, June 16, 2008
Please see directions for completing this document on the next page.
DATE: June 11, 2008
FROM: Anthony Raguine Community Development Department
x4739
TITLE OF AGENDA ITEM:
Consideration and approval of the release of the Tetherow Phase II performance bond and acceptance
of the maintenance bond.
PLTBLIC HEARING ON THIS DATE? No.
BACKGROUND AND POLICY IMPLICATIONS:
On November 26, 2007, the Board approved Improvement Agreement IA -07-11 (document # 2007-
569) for infrastructure (roads and utilities) for Phase II of the Tetherow Destination Resort, and
accepted the associated performance bond. The Road Department has verified (see attached memo)
that all improvments for Phase II are complete. Per the Improvement Agreement, the developer must
warrant that all improvements are free from defects in materials and workmanship for a period of 12
months, and warrant the improvments in the amount of ten -percent (10%) of the construction costs of
the required improvments. The construction costs for the Phase II improvements were $2,194,934.15.
The maintenance bond amount is $219,493.42.
Release of the performance bond occurs when the performance bond is removed from the Clerk's saf.
and sent to the developer. Prior to mailing the performance bond to the developer, the maintenance
bond will be placed in the Clerk's safe.
FISCAL IMPLICATIONS:
None.
RECOMMENDATION & ACTION REQUESTED:
Board release of the Tetherow Phase II performance bond, and acceptance of the maintenance bond.
ATTENDANCE: Anthony Raguine.
DISTRIBUTION OF DOCUMENTS:
Anthony Raguine
Legal Counsel
itM11L
InSC%1CD
CKG1aCD
INSCO INSURANCE SERVICES, INC.
Underwriting Manager for:
Developers Surety and Indemnity Company
Indemnity Company of California
17780 Fitch, Suite 200 • Irvine, California 92614 • (949) 263-3300
www.InscoDico.com
MAINTENANCE BOND
KNOW ALL MEN BY THESE PRESENTS:
THAT we, Proterra Bend 1, LLC
Corrected Original
BOND NO.: 785659S
, as Principal,
and Developers Surety and Indemnity Company , a corporation organized and doing business under
and by virtue of the laws of the State of lova and duly licensed to conduct surety
business in the State of Oregon , as Surety, are held and firmly bound unto
Deschutes County, Oregon
as Obligee, in the sum of Two Hundred Nineteen Thousand Four Hundred Ninety Three Dollars and Forty Two Cents --
($ 219,493.42 — ) Dollars, for which payment, well and truly to be made, we hind ourselves, our heirs, executors
and successors, jointly and severally firmly by these presents.
THE CONDITION OF THE OBLIGATION IS SUCH THAT:
WHEREAS, the above named Principal entered into an agreement or agreements with said Obligee to:
Improvements to roads and utilities for Phase 2 at the Cascade Highland/Tetherow Destination Resort IA -0711,
Deschutes County Document No. 2007-569.
WHEREAS, said agreement provided that Principal shall guarantee replacement and repair of improvements as described
therein for a period of one year following final acceptance by Obligee of said improvements;
NOW, TI-IEREFORE, if the above Principal shall indemnify the Obligee for all loss that Obligee may sustain by reason
of any defective materials or workmanship which become apparent during the period of one year from and after acceptance
of the said improvements by Obligee, then this obligation shall be void; otherwise to remain in full force and effect.
The bond is not subject to cancellation pursuant to ORS 742.366 (2)
1N WITNESS WHEREOF, the seal and signature of said Principal is hereto affixed and the corporate seal and the name
of the said Surety is hereto affixed and attested by its duly authorized Attorney -in -Fact
this 31st
Proterra Bend, LLC
day of March
2008
Principal
ID-1201(One Year Term) (REV. 5101)
YEAR
Developers Surety and Indemnity Company
BY:
He.ther Chesbro
Attorney -in -Fact
POWER OF ATTORNEY FOR
DEVELOPERS SURETY AND INDEMNITY COMPANY
INDEMNITY COMPANY OF CALIFORNIA
PO Box 19725, IRVINE, CA 92623 (949) 263-3300
KNOW ALL MEN BY THESE PRESENTS, that as except as expressly limited, DEVELOPERS SURETY AND INDEMNITY COMPANY and INDEMNITY COMPANY OF CALIFORNIA, do
each, hereby make, constitute and appoint:
***Eric Leagjeld, Cathy Poe, Stacy Gulnac, Heather Chesbro, Jeff Weichman, Chirs Intlekofer, jointly or
severally***
as their true and lawful Attomey(s)-in-Fact, to make, execute, deliver and acknowledge, for and on behalf of said corporations, as sureties, bonds, undertakings and contracts of suret/-
ship giving and granting unto said Attomey(s)-in-Fact full power and authority to do and to perform every act necessary, requisite or proper to be done in connection therewith as each of
said corporations could do, but reserving to each of said corporations full power of substitution and revocation, and all of the acts of said Attorney(s)-in-Fact, pursuant to these presen,s,
are hereby ratified and confirmed.
This Power of Attomey is granted and is signed by facsimile under and by authority of the following resolutions adopted by the respective Board of Directors of DEVELOPERS SURETY
AND INDEMNITY COMPANY and INDEMNITY COMPANY OF CALIFORNIA, effective as of January 1st, 2008.
RESOLVED, that the chairman of the Board, the President and any Vice President of the corporation be, and that each of them hereby is, authorized to execute Powers o
Attomey, qualifying the attorney(s) named in the Powers of Attomey to execute, on behalf of the corporations, bonds, undertakings and contracts of suretyship; and that the Secretary rr
any Assistant Secretary of the corporations be, and each of them hereby is, authorized to attest the execution of any such Power of Attorney;
RESOLVED, FURTHER, that the signatures of such officers may be affixed to any such Power of Attorney or to any certificate relating thereto by facsimile, and any such
Power of Attorney or certificate bearing such facsimile signatures shall be valid and binding upon the corporations when so affixed and in the future with respect to any bond, undertaki
or contract of suretyship to which it is attached.
IN WITNESS WHEREOF, DEVELOPERS SURETY AND INDEMNITY COMPANY and INDEMNITY COMPANY OF CALIFORNIA have severally caused these presents to be signed b!
their respective Vice President and attested by their respective Assistant Secretary this January 1st, 2008.
By:
By:
Stephen T. Pate, Senior Vice President
Charles L. Day, Assistant Secretary
State of California
County of Orange
On _ January 1st, 2008
personally appeared
Date
before me,
.+4-i ANO /4, 4,,,,
E.
'*"..`''PPORA"''' y
W i OCT. =11
;o" 1936 =-
'7�o xOWP......
ZJ
211
us
t7
pANrot.
�prPOgq,x
OCT. 6
1967
Christopher J. Roach, Notary Public
Here Insert Name and Title of the Officer
Stephen T. Pate and Charles L. Day
Name(s) of Signer(s)
,+ CHRISTOPHER J. ROACH
COMM. N 1746939
NOTARY PUBUC CALIFORNIA
ORANGE COUNTY
. 19. zn11 I
Place Notary Seal Above
who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to
the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized
capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of
which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of Califomia that the foregoing paragraph it
true and correct.
WITNESS my hand and offi ial seal.
Signature
Chi erJ.Roach
CERTIFICATE
The undersigned, as Assistant Secretary, of DEVELOPERS SURETY AND INDEMNITY COMPANY and INDEMNITY COMPANY OF CALIFORNIA, does hereby certify
that the foregoing Power of Attomey remains in full force and has not been revoked, and furthermore, that the provisions of the resolutions of the respective Boards of Directors of said
corporations set forth in the Power of Attomey, are in force as of the date of this Certificate.
This Certificate is executed in the City of Irvine, California, the 31 day of March , 2 0 0 8
By:
.V.VOrk0"1—
Albert Hillebrand, Assistant ecretary
1 D-1380(Wet)(R ev.07107 )
FEB -15-2008 FRI 02:00 PM Deschutes County Road FAX NO, 5413882719
P, 02/02
Road Department
MEMORANDUM
81150 SE 27th St. • pend, Oregon 97702
(841) 38S-8881 • FAX (541) See -2718
TO: ANTHONY 1ZAGUINE
FROM! GEORGE KOLB, COUNTY ENGINEER
SUBJECT! 1.1 714EROW RESORT BONDING; PHASII Al/A2
DATE! 2/15/2008
CC! JIM FROST; LAURIE CRAGHEAD
r.
The Road Department has verified that all improvements are completed for Phase A 1 /A2 of Tetherow
Resort, TP -06-973. The remaining bond amount for this project was $576,799.08. I have attached a letter
from W&H Pacific stating that all injprovements•have been installed in accordance to the plans approved
by Deschutes County.
Let me know if you need more information,
George
Quality Services Performed with Pride
ITEM
NO.
DESCRIPTION
TEHEROW RESORT
PHASE Al AND A2
STREET AND UTILITY
CONSTRUCTION COST
MAY 14, 2007
ESTIMATED UNIT
QNTY. PRICE
TOTAL
1. CLEARING AND GRUBBING INCLUDING OFF-SITE DISPOSAL FOR ROADS/ACCESS ROADS. 8.5 AC $ 2,075.00 $17,637.50
INCLUDES REMOVAL AND DISPOSAL OF TREES WITHIN RIGHT OF WAY.
]A. CLEARING AND GRUBBING FOR LOT FILLS, LOTS 1-6, 13-15.
2. FURNISH AND APPLY CONSTRUCTION WATER.
3. UNCLASSIFIED EXCAVATION AND EMBANKMENT
ESTIMATED EARTHWORK QUANTITIES ARE BASED ON
IN-PLACE VOLUMES, WITHOUT ADJUSTMENT FOR EXPANSION,
SHRINKAGE, SUBEXCAVATION OR SETTLEMENT.
THE ESTIMATED QUANTITY WILL BE THE FINAL PAY QUANTITY,
UNLESS A CHANGE ORDER IS EXECUTED FOR A CHANGE IN THE
WORK SCOPE.
ESTIMATED IN PLACE EXCAVATION: 11,800 CY
INCLUDES ALL ROADS AND ACCESS ROADS
ESTIMATED EMBANKMENT: 29,473 CY
INCLUDES ALL ROADS, LOT 1-6 FILLS, LOT 13-15 FILLS
3.6 AC $ 3,180.00 $1 1,448.00
I LS $48,000.00 $48,000.00
9,440 CY $ 11.10 $104,784.00
(80% of 11,800 CY)
2,250 CY $ 1.40
$3,150.00
(80% OF 2,812 CY, FROM BID ITEM #20)
17,783 CY $ 4.60
(OTHER ONSITE MATERIAL)
$81,801.80
4. FURNISH MATERIALS AND CONSTRUCT STANDARD 16" 6,670 LF $ 8.70 $58,029.00
VERTICAL CURB INCLUDING BASE ROCK UNDER CURB
PER DESCHUTES COUNTY STD. DWG. 2-2.
5. FURNISH MATERIALS AND CONSTRUCT 6,091 LF $ 7.90 $48,118.90
LOW PROFILE MOUNTABLE CURB INCLUDING BASE ROCK
UNDER CURB PER ODOT DRAWING NO. RD 700.
6. FURNISH MATERIALS AND CONSTRUCT 3/4" MINUS 20,440 SY $ 4.95 $101,178.00
AGGREGATE BASE COURSE, 6" MINIMUM COMPACTED
DEPTH FOR STREETS.
7. FURNISH MATERIALS AND CONSTRUCT 3/4" MINUS 2,200 SY $ 4.25 $9,350.00
AGGREGATE BASE COURSE, 4" MINIMUM COMPACTED
DEPTH FOR SEWER ACCESS ROAD
FURNISH MATERIALS AND CONSTRUCT 2" MINIMUM 20,440 SY $ 6.65 $135,926.00
COMPACTED DEPTH, CLASS C ASPHALT CONCRETE
PAVEMENT FOR STREETS.
9. FURNISH MATERIALS AND CONSTRUCT 2" MINIMUM 1,540 SY $ 7.00 $10,780.00
COMPACTED DEPTH, CLASS C ASPHALT CONCRETE
PAVEMENT FOR SEWER ACCESS ROAD.
10. FURNISH MATERIALS AND CONSTRUCT VARIABLE WIDTH
CONCRETE SURFACING (4" DEPTH W/2" BASE) INCLUDING
WHEELCHAIR RAMPS, HYDRANT PADS AND BIKE/
PEDESTRIAN RAMPS.
10A. FURNISH MATERIALS AND CONSTRUCT DRIVEWAY APRON
PER CITY OF BEND DETAILS 2-5,
860 SF $ 6.80 $5,848.00
90 SF $ 7.70 $693.00
10B. FURNISH MATERIALS AND CONSTRUCT A MULTI -USE PATHWAY WITH 2" MINIMUM 3,700 SY $ 8.15 $30,155.00
COMPACTED DEPTH, CLASS C ASPHALT CONCRETE.
G \Documents and Seth gsbnthonyaocal Skimps \Temporary Internet Files \OLK4133663-LAND-Me,ntenance nd-Desheles 2-1 C Isl
ITEM
NO,
DESCRIPTION
TEHEROW RESORT
PHASE Al AND A2
STREET AND UTILITY
CONSTRUCTION COST
MAY 14, 2007
ESTIMATED UNIT
QNTY. PRICE
TOTAL
IOC, FURNISH MATERIALS AND CONSTRUCT 3/4" MINUS AGGREGATE BASE COURSE,
4" MINIMUM COMPACTED DEPTH FOR MULTI -USE PATHWAY.
11. FURNISH MATERIALS AND INSTALL STREET NAME AND
STOP SIGNS PER COUNTY STANDARDS.
12. FURNISH MATERIALS, INSTALL AND MAINTAIN TEMPORARY
EROSION CONTROL DEVICES DURING CONSTRUCTION.
4,440 SY $ 3.40 $15,096.00
6 EA $ 590.00 $3,540.00
1 LS $ 640.00 $640.00
STREET CONSTRUCTION SUBTOTAL 8686,175.20
13. FURNISH MATERIALS AND CONSTRUCT
STANDARD CATCH BASIN PER DESCHUTES COUNTY
DRAWING NO. 3-3.
13A. FURNISH MATERIALS AND CONSTRUCT 4' WIDE CURB INLET
SIDEWALK CATCH BASIN PER CITY OF BEND STAND. SHT. 2-16
14. FURNISH MATERIALS AND CONSTRUCT STANDARD TYPE "B"
DRYWELL PER CITY OF BEND STD. DETAIL 2-12 WITH MINIMUM
30 CY OF DRAIN ROCK.
12 EA $ 915.00 $10,980.00
14 EA $ 1,060.00 $14,840.00
6 EA $ 4,800.00 $28,800.00
15. FURNISH MATERIALS AND CONSTRUCT STANDARD TYPE "B" 2 EA $ 5,000.00 $10,000.00
DRYWELL PER CITY OF BEND STD. DETAIL 2-12 WITH MINIMUM
50 CY OF DRAIN ROCK.
16. FURNISH MATERIALS AND CONSTRUCT STANDARD TYPE "B"
DRYWELL PER CITY OF BEND STD. DETAIL 2-12 WITH MINIMUM
100 CY OF DRAIN ROCK,
17. FURNISH MATERIALS AND CONSTRUCT SEDIMENTATION
MANHOLE PER DETAIL 4/C1.1.
18. FURNISH AND INSTALL 8" C900 PVC STORM DRAIN,
INCLUDING TRENCH EXCAVATION, BEDDING, AND BACKFILL.
18A. FURNISH AND INSTALL 10" C900 PVC STORM DRAIN,
INCLUDING TRENCH EXCAVATION, BEDDING, AND BACKFILL.
19. FURNISH AND INSTALL 12" C900 PVC STORM DRAIN,
INCLUDING TRENCH EXCAVATION, BEDDING, AND BACKFILL.
20. EXCAVATE GRADE, SHAPE, AND CONSTRUCT DRAINAGE
INFILTRATION BASINS.
2 EA $ 5,56500 $11,130.00
5 EA 1970 $9,850.00
940 LF $ 16.20 $15,228.00
190 LF $ 19.60 $3,724.00
510 LF $ 23.60 $12,036.00
2,812 CY $ 5.75 $16,169.00
21. FURNISH MATERIALS AND PLACE ODOT CLASS 100 RIPRAP 1 LS $2,350.00 $2,350.00
STORM DRAIN OUTFALL PROTECTIONS.
DRAINAGE CONSTRUCTION SUBTOTAL $135,107.00
22. FURNISH AND INSTALL 8" SANITARY SEWER, INCLUDING 2,005 LF $ 35.50 $71,177.50
TRENCH EXCAVATION, BEDDING, AND BACKFILL (0-6FT. DEPTH).
23. FURNISH AND INSTALL 8" SANITARY SEWER, INCLUDING 1,526 LF $ 45,00 $68,670.00
TRENCH EXCAVATION, BEDDING, AND BACKFILL (6-8 FT. DEPTH).
24. FURNISH AND INSTALL 8" SANITARY SEWER, INCLUDING 997 LF $ 46.00 $45,862.00
C'\Documents and SBNngs\anthony,\Local Settings \Temporary Internet Files \OLK4\33663-LAND-Maintenance Bond-Deahutes_2.145sla2
ITEM
NO.
DESCRIPTION
TEHEROW RESORT
PHASE Al AND A2
STREET AND UTILITY
CONSTRUCTION COST
MAY 14, 2007
ESTIMATED UNIT
QNTY. PRICE
TOTAL
TRENCH EXCAVATION, BEDDING, AND BACKFILL (8-10 FT. DEPTH).
25. FURNISH AND INSTALL 8" SANITARY SEWER, INCLUDING 761 LF $ 59.00 $44,899.00
TRENCH EXCAVATION, BEDDING, AND BACKFILL (10-12 FT. DEPTH).
26. FURNISH AND INSTALL 8" SANITARY SEWER, INCLUDING 508 LF $ 66.00 $33,528.00
TRENCH EXCAVATION, BEDDING, AND BACKFILL (12-14 FT, DEPTH).
26A. FURNISH AND INSTALL 8" SANITARY SEWER, INCLUDING 656 LF $ 90.00 $59,040.00
TRENCH EXCAVATION, BEDDING, AND BACKFILL (14+ FT, DEPTH).
27. FURNISH AND INSTALL 12" SANITARY SEWER, INCLUDING 78 LF $ 60.00 $4,680.00
TRENCH EXCAVATION, BEDDING, AND BACKFILL (8-10 FT. DEPTH).
28. FURNISH AND INSTALL 12" SANITARY SEWER, INCLUDING 21 LF $ 65.00 $1,365.00
TRENCH EXCAVATION, BEDDING, AND BACKFILL (10-12 FT. DEPTH).
29. FURNISH AND INSTALL 4" SAN. SEWER SERVICE, 3,290 LF $ 57.00 $187,530.00
INCLUDING TRENCH EXCAVATION, BEDDING, AND BACKFILL.
30. FURNISH MATERIALS AND CONSTRUCT STANDARD SEWER 49 EA $ 2,550.00 $124,950.00
MANHOLE, 48" ID, PER CITY OF BEND STD. DETAIL 3-3.
31. SANITARY SEWER STANDARD 48" ID MANHOLE CONSTRUCTION, 83 VLF $ 200.00 $16,600.00
IN EXCESS OF 8 FEET, VERTICAL DEPTH.
32. SANITARY SEWER TESTING PER CITY OF BEND SPECS. 1 LS $ 5,100 00 $5,100.00
SANITARY SEWER SUBTOTAL $663,401.50
32 FURNISH MATERIALS AND CONSTRUCT 8" CLASS 52 DUCTILE 5,880 LF $ 49.00 $288,120.00
IRON WATER MAIN, INCLUDING TRENCH EXCAVATION, BEDDING,
AND BACKFILL.
33. FURNISH MATERIALS AND CONSTRUCT 6" D.1. WATER LINE, 240 LF $ 44.00 510,560.00
INCLUDING TRENCH EXCAVATION, BEDDING AND BACKFILL.
34. FURNISH MATERIALS AND CONSTRUCT 1" COPPER WATER 2,580 LF $ 20.00 $51,600.00
SER VICE INCLUDING CORP STOP, TRENCH EXCAVATION, BEDDING
AND BACKFILL.
35. FURNISH MATERIALS AND INSTALL WATER SERVICE METER
BOX, METER STOPS, ANGLE VALVES, COUPLINGS, JUMPERS,
TAIL PIECES, AND APPURTENANCES PER CITY OF BEND
STD. DETAIL 4-6,
36. FURNISH MATERIALS AND CONSTRUCT FIRE HYDRANT
ASSEMBLY COMPLETE IN PLACE PER CITY OF BEND STD.
DETAILS 4-7 AND 4-8, WITHOUT BOLLARDS.
37. FURNISH MATERIALS AND INSTALL 8" GATE VALVE
ASSEMBLY PER CITY OF BEND STD. DETAIL 4-2.
38. FURNISH MATERIALS AND INSTALL 6" GATE VALVE
ASSEMBLY PER CITY OF BEND STD. DETAIL 4-2.
39. FURNISH AND INSTALL 8" X 8" X 8" TEE AND MECHANICAL
RESTRAINT SYSTEM PER CITY OF BEND SPECIFICATIONS.
C'\Decwnents end Seltings\anthonyr\Local SettirvetTemporary Internet Filee\OLK4\33661LAND-Maintenance Bon6Deahotee_2-1 Ur s3
68 EA $ 440.00 $29,920.00
16 EA $ 1,760.00 $28,160.00
19 EA $ 815.00 $15,485.00
16 EA $ 530.00 $8,480.00
4 EA $ 485.00 $1,940.00
ITEM
NO.
DESCRIPTION
TEHEROW RESORT
PHASE Al AND A2
STREET AND UTILITY
CONSTRUCTION COST
MAY 14, 2007
ESTIMATED UNIT
QNTY. PRICE
TOTAL
40. FURNISH AND INSTALL 8" X 8" X 6" TEE AND MECHANICAL
RESTRAINT SYSTEM PER CITY OF BEND SPECIFICATIONS.
12 EA $ 450.00 $5,400.00
41. FURNISH AND INSTALL 8" X 6" REDUCER. 4 EA $ 285.00 $1,140.00
42. FURNISH MATERIALS AND INSTALL 8%111/4° BEND AND 21 EA $ 315.00 $6,615.00
MECHANICAL RESTRAINT SYSTEM PER CITY OF BEND
SPECIFICATIONS.
43. FURNISH MATERIALS AND INSTALL 8"-22%° BEND AND 17 EA $ 320.00 $5,440.00
MECHANICAL RESTRAINT SYSTEM PER CITY OF BEND
SPECIFICATIONS.
44. FURNISH MATERIALS AND INSTALL 8"-45° BEND AND 1 EA $ 320.00 $320.00
MECHANICAL RESTRAINT SYSTEM PER CITY OF BEND
SPECIFICATIONS.
45. FURNISH MATERIALS AND INSTALL 8"-90° BEND AND 1 EA $ 335.00 $335.00
MECHANICAL RESTRAINT SYSTEM PER CITY OF BEND
SPECIFICATIONS.
46. FURNISH MATERIALS AND COMPLETE WATER LINE 1 LS $ 8,120.00 $8,120.00
CHLORINATION AND TESTING PER CITY OF BEND SPECIFICATIONS.
DOMESTIC WATER SUBTOTAL $461,635.00
47. CONSTRUCT FRANCHISE UTILITY TRENCH, INCLUDING TRENCH 6,650 LF $ 26.00 $172,900.00
EXCAVATION, BEDDING, AND BACKFILL.
48. FURNISH MATERIALS AND INSTALL 2" SCH. 40 PVC CONDUIT, 4,082 LF $ 1.10 $4,490.20
INCLUDING SWEEPS.
49. FURNISH MATERIALS AND INSTALL 3" SCH. 40 PVC CONDUIT, 2,485 LF $ 1.65 $4,100.25
INCLUDING SWEEPS.
50. FURNISH MATERIALS AND INSTALL 5" SCH. 40 PVC CONDUIT, 3,675 LF $ 3.00 $11,025.00
INCLUDING SWEEPS.
50A FURNISH MATERIALS AND INSTALL 3 PHASE SECTIONALIZING CABINET, 5 EA $ 2,650.00 $13,250.00
575-TRANS-PCORP PAD VAULT, STOCK ITEM 172063.
51. FURNISH MATERIALS AND INSTALL PACIFIC POWER SINGLE 19 EA $ 2,000.00 $38,000.00
PHASE TRANSFORMER PAD VAULT, 644-PCORP. STOCK ITEM 4179005
52. FURNISH MATERIALS AND INSTALL PACIFIC POWER, SINGLE 1 EA $ 4,850.00 $4,850.00
PHASE SECTIONALIZING CABINET PADVAULT, 776-PCORP, 6X6 MH -INCIDENTAL
TRAFFIC VAULT, STOCK ITEM 1720626.
DRY UTILITIES CONSTRUCTION SUBTOTAL $248,615.45
TOTAL SCHEDULE BID A AMOUNT $2,194,934.15
Total Bid in
Figures
Maintenance Bond Amount: $219,493.42
C \Documents end Seltinps\anthonyr\Local Seltings\Temporary Internet F,tes\0LKa133663-LAND-Maintenance Bon6Deshutes_2-I la'