June 3, 2009
Board of County Commissioners
Erik Kropp, Deputy County Administrator
Re: Energy Efficiency and Conservation Block Grant Request
Deschutes County has been allocated $325,700 in a direct formula grant as part of the U.S.
Department of Energy's Energy Efficiency and Conservation Block Grant (often referred to as
"energy stimulus"). The purpose of the program is to develop, promote, implement, and manage
energy efficiency and conservation projects.
Once awarded, entities have three years to spend the funds. No matching funds are required, but
an application must be submitted and an Energy Efficiency and Conservation strategy must be
developed within 120 days of grant award. This strategy includes measurable goals and
objectives for energy efficiency and conservation.
Recommended projects for these grant funds include -
1. Building light retrofits resulting in energy savings — for example, Mike Maier Building,
Justice Building, OSP, Road Department, Unger Building, Transitional House,
Downtown Health Center, etc.
2. Heating, Ventilating, and Air Conditioning (HVAC) upgrades to more energy efficient
units — for example, OSP, Unger Building, and the Annex building.
3. Electrical upgrade resulting in energy savings — Deschutes Historical Society Building.
($213,700 is recommended for items 1 — 3)
4. CDD Energy Code Building Inspector ($80,000) — a Building Safety Inspector FTE
(temporary, up to 12 -months) would perform inspections and plan reviews related to
structural energy efficiency. The position could also provide analysis of the ICC
(International Code Council) for adoption in Deschutes County.
5. Shared contract position with the City of Bend ($32,000 over 3 years for the County;
Bend has committed $66,000 over 3 years) - this position would serve as an energy
resource coordinator. For Deschutes County, the position would assist in the
development of the Energy Efficiency and Conservation strategy, assist in project
development, and provide project management on energy efficiency projects.
Other requested projects -
1. CDD software replacement ($200,000) — CDD's permit system is slated for replacement
by the State's Accela system at no direct cost to the County (due to the statewide
surcharge on building permits). However, the Accela system modules that support land
use planning, environmental health, and code enforcement will need to be purchased by
CDD. The Accela system is compatible with remote access devices ('Notebook' laptop
devices). Providing field staff with remote devices will reduce vehicle trips. In addition,
software features have the potential to reduce customer trips as well. The software
replacement is a necessity at some point in the future.
2. Commute Options, Regional Transportation Demand Management (TDM) Program
Enhancement ($30,000) — implement and enhance the County's TDM program and create
Transportation Association strategies for the northern region of the County.
3. Park and ride lot study, Commute Options ($33,000) — comprehensive needs study of
Deschutes county park and ride facilities.
4. Wickiup Junction Park and Ride lot upgrades, Commute Options ($20,000) — grading,
rock base, rail fencing, and general improvements.
Other Projects for Competitive Grant Application Process -
1. Solar projects through the State Energy Program— Deschutes Services Building, Fair and
Expo's Event Center.
2. Brownfield funds to assist with the environmental clean-up of the shooting range.
3. Electric car charging stations.
4. Electric/hybrid cars and trucks.
Attachments:
• Commute Options detailed projects request
c: Dave Kanner, County Administrator
Tom Blust, Road Department Director
Tom Anderson, Community Development Director
Susan Ross, Property and Facilities Director
Judith Ure, Management Analyst
Proposal to Deschutes County. Prepared by Jeff Monson, Executive Director,
Commute options for Central Oregon
June 2, 2009
Background:
Energy Efficiency and Conservation Block Grant Program
• A grant program that is funded through the American Recovery and
Reinvestment Act (ARRA).
• The Deschutes County is a direct entitlement recipient.
What is the purpose of the grant program?
The purpose of the EECBG Program is to assist eligible entities in creating and
implementing strategies to:
• Reduce fossil fuel emissions in a manner that is environmentally sustainable and,
to the maximum extent practicable, maximizes benefits for local and regional
communities;
• Reduce the total energy use of the eligible entities; and
• Improve energy efficiency in the transportation sector, in building sector, and
other appropriate sectors.
What specific activities are eligible for use of funds?
Funds can be used community wide, not only for government owned facilities and
infrastructure. The following activities are eligible:
• Development and Implementation of Transportation Programs to conserve
energy.
How will success be measured?
Grantees are required to report quarterly to the DOE on five metrics for each project or
activity:
1. Jobs created and/or retained
2. Energy savings on a per dollar invested basis
3. Renewable energy capacity installed
4. Greenhouse gas emissions reduced
5. Funds leveraged
See page two
Deschutes County project proposals:
A. Regional Transportation Demand Management Program Enhancement
Estimated cost per year: $30,000
Implement and enhance the County's TDM Program and create Transportation
Management Association (TMA) strategies for the northern region of the County.
See attachment A
B. County park and ride Tots
Park and ride lot study
$33,000
• Comprehensive needs study of Deschutes county park and ride facilities
See attachment B and C
Park and ride lot signs $15,000
• Replace signs at all Tots and highway directional signs
Wickiup Junction Park and Ride lot upgrades $20,000
Grading, rock base, rail fencing, general improvements. (We need some Road
Department input on this project — what is needed and cost)
Attachment A
Scope of Services, with energy savings.
DOE Energy Block Grant
Commute Options for Central Oregon/Deschutes County
2008, 2009
Deschutes County will provide funding to Commute Options for Central Oregon to assist
with the management of Transportation Demand Management (TDM) strategies in the
county. Commute Options will implement long-term program development, outreach
and partnership -building to engage various community interests in TDM. The following
outlines Commute Options' estimated commitment to Deschutes County.
Transportation Management Association aspect of the project:
• Prepare and submit quarterly reports that demonstrate Commute Options'
progress. Deliverable: Submit quarterly reports.
• Provide information, assistance and support to County area employers in
developing and implementing TDM programs, especially in the NE Bend area
and Juniper Ridge. Deliverable: Contact 10 businesses and establish TDM
employee programs.
Energy savings: 100 employees x 45 days x 20 miles = 90,000 vehicle miles reduced.
Incentives aspect of the project:
$20.00 incentives will be distributed for every 95 round trips reduced.
• Work to establish carpool matching. Deliverable: Increase ridership from Sisters,
Sunriver, LaPine, Deschutes River Woods, Redmond and Black Butte Ranch.
Energy savings: Carpools, 25 carpools with 60 employees x 45 days x 40 miles =
108,000 vehicle miles reduced.
• Assist with establishing a county -wide employee incentive program.
Energy savings: 90 employees x 135 days x 12 miles = 145,800 vehicle miles reduced.
Total energy savings estimated at 343,800 motor vehicle miles reduced.
Grant amount: $30,000 (About 11 cents per mile reduced)
DRAFT
Park -and -Ride Master Plan for Central Oregon
Prepared by Tyler Deke
Definitions
GIS: Geographic Information Systems
PMT: Project Management Team
SOW: Scope of Work
Agency: Commute Options for Central Oregon
Contractor: Consultant firm hired to complete identified work
November 19, 2008
General Assumptions and Requirements
All work products must be provided in hard copy and in electronic format (Microsoft Word and
Excel). All mapping products must be submitted in hard copy and in electronic format
compatible with ArcGIS software.
While technical memorandum tables, charts, graphs, and maps may have color; each must be
reproducible in black and white.
The planning area for this project consists of the Central Oregon area (Deschutes, Jefferson,
and Crook Counties).
Contractor shall be responsible for satisfactory completion of project deliverables, regardless of
references to "support" by Agency, as specified in this Contract within the overall timeframe and
scope of work provided by the SOW.
Contractor shall provide Agency with an opportunity to review and provide input on all
Contractor deliverables throughout the project. Contractor shall make revisions in response to
Agency and PMT input prior to each deliverable being considered complete. Budget assumes
one round of review and comment on deliverables.
Contractor shall be responsible for scheduling, initiating, and maintaining monthly
communication on project status and issues with Agency either via a conference call, a written
progress report (e-mail acceptable) or at a scheduled coordination meeting. A copy of
progress/status report must be submitted with monthly invoice.
Agency shall provide meeting space for all coordination meetings. Agency project manager shall
attend all meetings.
Agency shall provide Contractor with access to available existing local inventory records and
participate in data collection as appropriate and necessary.
Purpose and Scope
Deschutes, Jefferson, and Crook Counties are home to thousands of people who commute
regularly to jobs outside the city and/or county where they live. These long-distance commutes
have a significant impact on roadway volumes and also contribute to air pollution. Park -and -
Ride lots are vital "change of mode facilities" where individuals meet and then group -travel to
their destinations via vanpool, carpool or transit. If the regional park-and-ride program is to keep
pace with the increase predicted in long-distance commuting, provisions must be made to make
new park-and-ride lots an integral part of the transportation system. The purpose of the Park-
DRAFT
November 19, 2008
and -Ride Master Plan for Central Oregon is to provide a Tong -range comprehensive guide for
developing the park-and-ride system.
The plan will describe the existing facilities in Central Oregon, their condition and their current
level of use. It will also identify future needs for park-and-ride based on expected growth and
commute patterns, and available transit services. The number of spaces and potential locations
of future park-and-ride lots will be provided in the plan. Desirable features for future lots should
be described including signage, lighting, fencing, landscaping, and bus shelters. Cost estimates
for construction and amenities will be provided for new park-and-ride lots based on several
prototype lots of varying sizes.
Opportunities for funding the park-and-ride expansion program from federal, state, regional local
and private sector sources will also be identified.
DRAFT
Work Program
November 19, 2008
Task 1: Project Management
Objective
Manage project to assure delivery of high quality products within budget and schedule.
Methods
1.1 Project Management — Contractor responsibilities include development of project
schedule, regular communications with Agency project manager, oversight and
coordination of project team, quality assurance, and preparation of monthly progress
reports and invoices. The monthly progress report must include previous month's project
activities and percent completed of each task, the planned activities for the next month,
and identify issues and/or concerns that may affect the project or schedule.
1.2 Presentations to Boards & Commissions — Contractor will assist Agency with
development of presentation materials for at least two presentations to the Central
Oregon Area Commission on Transportation (COACT) and one additional presentation
to an area board or commission (to be determined by TAC).
1.3 Technical Advisory Committee meetings - Agency shall establish a Technical Advisory
Committee (TAC) to provide technical review and guidance. Contractor shall convene
two (2) TAC meetings (in person or via phone). Agency shall prepare meeting
summaries and distribute via e-mail within 10 business days of each meeting.
Schedule
Throughout the contract agreement timeframe
Deliverables
Assumptions
• Agency project manager will determine dates for presentations to Boards and
Commissions
• Agency project manager will identify members for the TAC. Agency project manager will
work with Contractor to identify meeting dates/times for TAC.
Task 2: Inventory of Existing Lots
Objective
To understand and document existing park and ride lot locations, capacities, conditions,
utilization, lot area land use (existing, zoning, and general plan), and accessibility by
transportation mode (pedestrian, bicycle, transit). System inventory data and local transportation
system plans shall be used to describe existing conditions of the park and ride lot system.
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the inventory.
Contractor
Agency
Regular communications with Agency project manager
Lead
Support
Monthly invoices and progress reports
Lead
Lead/Support
Support
Lead/Support
Three (3) Presentations to Boards & Commissions
Two 2 TAC meetin • s
Lead
Lead/Support
Assumptions
• Agency project manager will determine dates for presentations to Boards and
Commissions
• Agency project manager will identify members for the TAC. Agency project manager will
work with Contractor to identify meeting dates/times for TAC.
Task 2: Inventory of Existing Lots
Objective
To understand and document existing park and ride lot locations, capacities, conditions,
utilization, lot area land use (existing, zoning, and general plan), and accessibility by
transportation mode (pedestrian, bicycle, transit). System inventory data and local transportation
system plans shall be used to describe existing conditions of the park and ride lot system.
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the inventory.
DRAFT
November 19, 2008
2.1 Inventory — Contractor shall prepare an inventory of the existing park and ride facilities.
The inventory shall identify lot locations, lot capacities, lot conditions, and lot utilization.
2.2 Area land use - Contractor shall prepare a description of the planning area and land use
based on existing city and county information in the planning area.
2.3 Transportation system access - Contractor shall evaluate system conditions and access
for autos, bikes, pedestrians, and transit.
2.4 Mapping — Contractor shall develop a consistent ArcGIS based map template to support
existing conditions reporting for relevant figures included in the existing conditions
documentation. Contractor shall prepare up to 12 maps for use in the existing conditions
and deficiencies documentation using the standard template using available GIS
databases assembled by the cities and counties.
2.5 Inventory and existing conditions — Contractor shall prepare an existing conditions report
based on the analysis completed in tasks 2.1 through 2.4.
Schedule
Months 1-3
Final Existing Conditions Report due by end of month 3
Deliverables
Task 3: Future Park and Ride Needs Assessment
Objective
Assess the need for future park-and-ride capacity by evaluating sites where demand is
exceeding capacity, informal park-and-ride is occurring, new development is planned, and areas
that may be served by transit.
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the assessment.
3.1 Evaluate sites where current demand is exceeding available capacity.
3.2 Evaluate sites where informal park-and-ride is occurring.
3.3 Evaluate sites where new development is planned.
3.4 Evaluate sites that are currently or may be served by transit.
Schedule
Months 3-5
Final Needs Assessment due by end of month 5
liverables
Contractor
Agency
Technical memorandum describing existing transportation
system conditions, including maps and appendices.
Lead
Support
Task 3: Future Park and Ride Needs Assessment
Objective
Assess the need for future park-and-ride capacity by evaluating sites where demand is
exceeding capacity, informal park-and-ride is occurring, new development is planned, and areas
that may be served by transit.
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the assessment.
3.1 Evaluate sites where current demand is exceeding available capacity.
3.2 Evaluate sites where informal park-and-ride is occurring.
3.3 Evaluate sites where new development is planned.
3.4 Evaluate sites that are currently or may be served by transit.
Schedule
Months 3-5
Final Needs Assessment due by end of month 5
liverables
Contractor
Agency
Technical memorandum assessing the need for future park -and-
ride capacity by evaluating sites where demand is exceeding
capacity, informal park-and-ride is occurring, new development
is planned, and areas that may be served by transit.
Lead
Support
DRAFT
Task 4: Assessment of Future Lot Locations
Objective
Assess the need to expand existing lots and construct new lots.
November 19, 2008
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the assessment.
4.1 Assess the need to expand existing Tots
4.2 Assess the need to construct new lots
Schedule
Months 5-7
Final Assessment due by end of month 7
Deliverables
Task 5: Cost Assessment
Objective
Assess the costs of upgrading existing Tots and constructing new lots.
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the cost assessment.
5.1 Cost Estimates for expanding existing lots and constructing new lots
5.2 Potential 5- and 10 -year capital improvement programs
Schedule
Months 7-8
Final Cost Assessment due by end of month 8
Deliverables
Contractor
Lead
Agency
Support
Technical memorandum assessing the need to expand
existing Tots and construct new Tots.
Task 5: Cost Assessment
Objective
Assess the costs of upgrading existing Tots and constructing new lots.
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the cost assessment.
5.1 Cost Estimates for expanding existing lots and constructing new lots
5.2 Potential 5- and 10 -year capital improvement programs
Schedule
Months 7-8
Final Cost Assessment due by end of month 8
Deliverables
Task 6: Funding Assessment
Objective
Assess possible funding opportunities to implement the plan.
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the funding assessment.
6.1 Assessment of funding options
6.2 Recommended funding strategy
Contractor
Agency
Technical memorandum providing detailed cost estimates
for expanding existing lots and constructing new Tots and
potential 5- and 10 -year capital improvement programs.
Lead
Support
Task 6: Funding Assessment
Objective
Assess possible funding opportunities to implement the plan.
Methods
Contractor shall work with Agency project manager to develop and agree on an outline for
developing the funding assessment.
6.1 Assessment of funding options
6.2 Recommended funding strategy
DRAFT
Schedule
Months 8-9
Final Funding Assessment due by end of month 9
Deliverables
November 19, 2008
Contractor
Agency
Technical memorandum assessing funding options and a
recommended funding strategy.
Lead
Support