BEFORE THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES COUNTY, OREGON
An Ordinance Amending Ordi-
nance PL -15, Deschutes County * L" 1
Zoning Ordinance of 1979, as * l� L^ E
Amended, Rezoning Certain
Property From Exclusive Farm AU
Use - 20 (EFU-4 ) Zone to G 2 6 1982
Airport Development (AD) Zone,* ROSE
and Declaring an Emergency. * DESCHUTES NTTERSON
Y CLERK
ORDINANCE NO. 82-031
WHEREAS, the City of Bend, a municipal corporation, proposed
the rezoning of certain property from Exclusive Farm Use - 20
(EFU-4) Zone to Airport Development (AD) Zone; and
WHEREAS, notice of hearing was given in accordance with law;
and
WHEREAS, the Deschutes County Planning Commission held a
hearing on the proposed zone change on June 9, 1982; and
WHEREAS, the Deschutes County Planning Commission recommended
that the property be rezoned from Exclusive Farm Use - 20 (EFU-4)
Zone to Airport Development (AD) Zone by decision dated June 23,
1982; and
WHEREAS, the decision of the Deschutes County Planning Com-
mission has not been appealed to the Deschutes County Board of
Commissioners; now, therefore,
THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES COUNTY,
OREGON, ORDAINS as follows:
Section 1. That Ordinance No. PL -15, Deschutes County Zoning
Ordinance of 1979, is amended to change the zoning from Exclusive
Farm Use - 20 (EFU-4) Zone to Airport Development (AD) Zone for
the parcel of real property described as:
Tax Lots 200 and 300 in Section Twenty (20),
Township Seventeen (17) South, Range Thirteen
(13) East of the Willamette Meridian,
Deschutes County, Oregon, and Tax Lot 200 in
Section Seventeen (17), Township Seventeen
(17) South, Range Thirteen (13) East of the
Willamette Meridian, Deschutes County,
Oregon;
1 - ORDINANCE NO. 82-031
VOL `"43wE 952
and depicted on the map marked Exhibit "A", attached hereto and by
this reference incorporated herein.
Section 2. To adopt as the Board of County Commissioners'
findings and conclusions, the findings and decisions of the
Deschutes County Planning Commission dated June 23, 1982, relating
to Zone Change Application Number Z-82-5, marked Exhibit "B",
attached hereto and by this reference incorporated herein.
Section 3. This ordinance being necessary for the immediate
preservation of public peace, health and safety, an emergency is
declared to exist, and th}'s ordinance takes effect on its passage.
DATED this the day of /�u �f , 1982.
BOARD OF COUNTY COMMISSIONERS
OF EHUTES COU Y, OREGON
CL Y- . SHEPARIY, Chairman
Le Tei �! e
ALBERT A. YOUNG, Commissioner
SRT C: PAULSON, JR.,C�ssloner
ATTEST:
J, W'
SUSAN STONEMAN
Recording Secretary
2 - ORDINANCE NO. 82-031
EXHIBIT "A"
T
Noft1
SECTION 20 T.17S. R.13E.W.M.
DESCHUTES COUNTY
i"=aoo'
Z-82-5
C -A L4 o f Ben<i
1-7-13-:20 Tax LoVs
200 and 300
A A nr►n
EXHIBIT "A
VOL-43PAGE 954
ti
ro
ti
FILE NO.
Z-82-5
A PPT.TrANT
COURTHOUSE ANNEX, ROOM 102 • PHONE 388-6556
BEND, OREGON 97701
FINDINGS AND DECISION
VOL ~43PAGE 955
CITY OF BEND, a Municipal Corporation
REQUEST
An Application to zone approximately 340 acres from Exclusive Farm
Use - 20 (EFU-4) Zone, to Airport Development (AD) Zone.
LOCATION
The subject property is located easterly of the intersection of
Butler Market Road and Powell Butte Highway, and is described as
Tax Lots 200 and 300 in Section Twenty (20), Township Seventeen
(17) South, Range Thirteen (13) East of the Willamette Meridian,
Deschutes County, Oregon, and Tax Lot 200 in Section Seventeen
(17), Township Seventeen (17) South, Range Thirteen (13) East of
the Willamette Meridian, Deschutes County, Oregon.
PLANNING STAFF RECOMMENDATION
Approval.
PUBLIC HEARING
Public hearing was held in Conference Room A, Deschutes County
Courthouse Annex, Bend, Oregon, on June 9, 1982, at 7:30 p.m.
BURDEN OF PROOF
Section 6.000 of Deschutes County Ordinance PL -9, as amended,
Deschutes County Procedural Ordinance, provides:
"(1) The burden of proof is upon one seeking the
change. The degree of that burden increases propor-
tionately with the degree of impact of the change which
is sought.
1 - FINDINGS AND DECISION
EXHIBIT "B"
VOL __ 43PAGE 956
(2) The Applicant shall, in all cases, establish:
(a) Conformance with the Comprehensive Plan; and
(b) Conformance with all applicable statutes; and
(c) Conformance with all applicable ordinance
provisions setting forth the various criteria
to be employed for rezoning . . . ; and
(d) Conformance with Statewide planning goals
whenever they are determined to be appli-
cable.
(3) In addition to the requirements of subsection (2)
of this section, the applicant shall, in the case of a
requested rezoning establish:
(a) That there is a public need for a change of the
kind in question; and
(b) That the need will be best served by changing the
classification of the particular piece of property
in question as compared with other available
property."
EVIDENCE
Evidence on behalf of the Applicant, City of Bend, was presented
by Phillip Young, Mayor of the City of Bend; Jay Turley, Assistant
City Manager; Ron Marceau, City Attorney; and excerpts of prior
testimony submitted by City Attorney, consisting of testimony of
John Andersen, in written form, and testimony of Ray Costello, in
written form; a written transcript of a hearing before the Board
of County Commissioners dated December 21, 1979; and a letter from
the Department of Transportation, Federal Aviation Administration,
dated December 16, 1980.
Testimony in opposition to the Application was presented by Al
Holden, Margaret Saul, James Saul, Ken Cale, and Dorothy A. Cale.
Evidence presented by Deschutes County in the form of its Staff
Report, recommended approval, finding that the Applicant had
sustained his burden of proof, that the Application was in con-
formance with the Comprehensive Land Use Plan applicable statutes
and ordinances, and that because the Deschutes County Comprehen-
sive Plan had received compliance acknowledgment from the Land
Conservation and Development Commission, was in conformance with
all Statewide Planning Goals. Staff found that there was a public
2 - FINDINGS AND DECISION
EXHIBIT "B"
vol 43PAGE 957
need for the change of the kind in question, and that it would be
best served by changing the classification of the particular piece
of property in question as compared with other available property.
Other evidence noted is Ordinance No. 80-222, and Ordinance relat-
ing to the Deschutes County Year 2000 Comprehensive Plan, and
Ordinance No. 80-221 adopting Section 4.160, Airport (AD) Zone.
SUPPORTING TESTIMONY
1. Testimony of Phillip Young:
Phillip Young asked the Commission to change the zoning of the
Airport to Airport Development (AD) Zone, referring to the
Deschutes County Comprehensive Plan which was amended one year ago
to incorporate the Airport into the Comprehensive Plan. He indi-
cated that the Land Use Board of Appeals had confirmed the Plan,
as amended, and that the zone change would bring the zoning into
conformance with that Plan. He stated that the Airport had been
in existence since 1942, and is now being used by 120 local
residents.
2. Testimony of Jay Turley:
Jay Turley testified that City, County, State and Federal govern-
ments have significant investments in the Airport, and that the
change in zoning is necessary to take advantage of the public
investment in a manner that is consistent with the governmental
bodies' public trust. Mr. Turley made reference to the written_
testimony of Mr. Costello indicating that Federal and State
officials are of the opinion that it would be impossible to locate
the Airport in any other area of Deschutes County. He testified
that it would be necessary that 340 acres be rezoned since all are
used for Airport purposes. He testified that airport planning is
very similar to other transportation systems, and that the State
will develop a blueprint and then it is put into the national
plan. He testified that the Bend and Redmond Airports are part of
that State and national plan. He distinguished the Redmond
Airport as an air carrier airport, which basically serves as a
commercial aircraft facility. The role of the Bend Airport is
that of a general aviation airport for very light aircraft. The
roles of both airports are important to both Bend and Redmond, and
benefit all of Central Oregon. He stated that the future will
show the investment to be a wise investment, particularly for the
local economy and transportation systems that are a vital part of
encouraging economic growth within the Bend area.
3. Testimony -of Ron Marceau:
Ron Marceau stated that every square inch of the Airport is used
for airport purposes. Part of the Airport is being used for
3 - FINDINGS AND DECISION
EXHIBIT "B"
von-43PAGE 958
runways and hangars, some for buildings, and the rest being used
to contain Airport noises and to give room to maneuver and accom-
odate planes having safety problems. Mr. Marceau submitted
written testimony by John Andersen, Ray Costello of the State
Board of Aeronautics, and Mark Beisse of the Federal Aviation
Commission. He also introduced a letter dated September 16, 1980,
from the Federal Aviation Administration. Mr. Marceau testified
that the Comprehensive Plan change approved by the Land Use Board
of Appeals permits rezoning to AD for the Airport property itself.
He testified that property around the Airport may be considered
for a zone change when the time is right. He stated that since
the Board of County Commissioners decided not to change the
Comprehensive Plan for other properties, just the Airport can be
considered for rezoning at this time. He distinguished the Bend'
Airport from the Redmond Airport, and testified that the two
facilities complement each other. In response to a question from
Chairman Quackenbush, Mr. Marceau testified that AD Zone allows,
as uses permitted, Airport uses and Airport related commercial
uses. All other uses are conditional.
4. Written Testimony:
A. Prior written testimony of John Andersen. The testimony
summarized the location and history of the Bend Airport, showing
that there is a need to assure Airport growth is compatible with
the maintenance of rural character existing in the area. Mr.
Andersen's testimony also stated that it is important from the
County's perspective that adequate transportation facility is
provided for the City of Bend, as regards air transportation. The
testimony made reference to the Exceptions Statement adopted with
the Comprehensive Plan Amendment, which supports taking exception
to Agricultural Goal 3 for the Airport property. Mr. Andersen
identified the agreement of the City of Bend and Federal govern-
ment that provided the Airport property be transferred on the
condition that it continue as a airport facility. The City has
agreed with the Federal Aviation Administration for ADAP funds to
continue the Airport for the next twenty years. The report
"Airport Compatibility Planning", by the Oregon Department of
Transportation, Aeronautics Division, when reviewed in conjunction
with the Airport Plan, shows the majority of lands within the 65
LDN in the Year 2000 Forecast within the Airport property. The
Bend Airport Master Plan outlines the current City ownership of
the Bend Airport, showing current uses and buffers on the pro-
perty. John Andersen's testimony identified the Airport Height
Combining (AH) Zone which was established based on the recommen-
dation of the Airport Master Plan to prohibit obstructions within
the zone for the safety of pilots taking off and landing from the
Airport facility. The testimony supported that the Airport is the
key facility that meets the needs of the rural and urban residents
within the Bend area, that there are no alternative locations
within the area that could be used for the proposed purpose, and
4 - FINDINGS AND DECISION
EXHIBIT "B"
VOL 49PAGE 959
the City is committed to maintaining the Airport as mentioned
above, due to financial and environmental difficulties associated
with any new location.
B. Written testimony of Ray Costello:
The testimony of Ray Costello emphasized that airports historical-
ly have been located in agricultural areas, and there is no con-
flict between agriculture and airport uses. Mr. Costello iden-
tified the different role of the Redmond Airport as opposed to the
Bend Airport. Mr. Costello identified that most -agricultural
activity in the vicinity of the Bend Airport is the grazing of
large animals, which probably is the least conflicting agricultur-
al use with airport uses. Mr. Costello testified that all of the
Airport property is necessary, since maneuverability and clear
zones are necessary in order to utilize airport property. Mr.
Costello testified that the Airport will probably increase in
usage in the future, but that the Federal Aviation Administration
is developing new noise regulations, which should lessen the noise
impact in the future. Mr. Costello indicated that it would be
impossible to relocate the Airport in any other location. Mr.
Costello testified that airports were being lost nationwide at
approximately 200 per year, and that the capacity of airports has
increased from 13% in 1974 to approximately 60% currently.
C. Written testimony of Mark Beisse.
Mr. Beisse testified that the present use of the lands around the
Bend Airport is the best use of the land. 3,000 airports out of
approximately 14,000 airports across the country are considered
essential to the FAA system. The Bend Airport is one of those
3,000 essential airports. He reiterated that the Redmond Airport
is an air carrier airport to serve larger airplanes. Bend only
serves the smallest airplanes. Mr. Beisse felt that the Master
Plan should be incorporated in the Comprehensive Land Use Plan,
and that the ADAP funding for the facility will continue.
D. Written testimony of Department of Transportation -
letter dated December 16, 1980.
The written testimony indicated that the Federal Aviation Admin-
istration had approved the Airport Layout Plan, and felt that it
provided a sound basis for managing the growth of the Airport. It
indicated that existing agricultural zoning is most compatible
with airport operations, and airport uses are common near airports
and few problems encountered in cases from either aeronautical or
agricultural users. Industrial zoning would be next in order of
desirability, although potential problems with construction, etc.,
should be closely monitored. The letter from the Federal Aviation
Administration noted that the Bend Municipal Airport is considered
5 - FINDINGS AND DECISION
EXHIBIT "B"
VOL "` Una 960
essential to the national airport system, and has a utility role
which complements rather than duplicates activities at the Redmond
Municipal Airport.
DISTINGUISHING ADVERSE TESTIMONY
1. Testimony of Al Holden:
Al Holden testified that the Airport didn't belong where it has
been located since 1942. He felt that all airport traffic should
be handled through the Redmond Airport. The Planning Commission,
based on evidence presented by the City, and the explanation of
City Attorney, determines that the Applicant's evidence shows that
the facility services a different type of airplane and usage, and
that the investment by the City in this location, along with the
inability to establish new airports, make the current Bend Airport
site the only feasible site for airport use and the AD
designation.
2. Testimony of Margaret Saul:
Margaret Saul's main contention was that if the Airport was to
receive AD zoning, her property should receive the same zoning
since it is close the the Airport and impacted by noise. The Year
2000 Comprehensive Plan of Deschutes County provides that when
noise impacts spread to the property, it will be eligible for an
exception if there is a need for such zoning at that time. Since
Mrs. Saul primarily was interested in having her own property
rezoned, the Planning Commission feels that they are unable to
address such a desire without an application before them. The
fact that a neighboring property is not being rezoned is not a
sufficient factual basis to withhold zoning from the Applicant's
property.
3. Testimony of Ken Cale:
Ken Cale testified in opposition to the Airport because he felt
that the present Airport projects a runway onto his property. His
objection was that the City may ultimately acquire his property
through an eminent domain procedure. His other concern related to
the fact that his property was not being zoned AD like the Air-
port. The Planning Commission feels both issues are not related
to zoning, and that any eminent domain procedure is an action unto
itself. Additionally, when and if his property falls within the
noise corridor level, as shown in the Comprehensive Plan, it will
be eligible for rezoning. Since his property is not the subject
of the current Application, the Planning Commission feels it
cannot consider whether or not that property should be also
upzoned to AD zoning.
6 - FINDINGS AND DECISION
EXHIBIT "B"
VOL -. 43PAGE MI
4. Testimony of James Saul:
James Saul objected to the Airport because his property is within
200 feet of the Airport property. He also questioned the need to
have 340 acres of property for AD zoning. The Planning Commission
felt that the testimony of the City adequately defended the size
of the parcel for zoning AD, since those portions not actually
occupied by buildings and runways were used to contain noise
levels, and for emergency landings.
5. Testimony of Dorothy Smead Cale.
Dorothy Smead Cale testified that she had managed the Airport, and
the Airport had never bothered their cows. She indicated that she
had owned a portion of the Airport property and had sold it to the
City. She said she had never been against the Airport, but she
had never been contacted about the land possibly taken away be-
cause of the Comprehensive Plan. She requested the emphasis be
placed on the Redmond Airport, and keep the Airport a small air-
port. The Planning Commission did not feel that this testimony
was necessarily in opposition to the Airport zoning on Applicant's
property. This is especially true, taking cognizance of the fact
that any expansion is subject to site plan and possible condition-
al use application, felt that growth of the Airport would be
minimal.
FINDINGS
1. Airport Development (AD) Zone is appropriate zoning for an.
airport facility.
2. The 340 acres of property under the ownership of the City of
Bend is currently being used for airport uses.
3. All of the property is used in some manner for airport or
airport -related uses.
4. Surrounding agricultural uses are compatible with airport
uses on the Airport property.
5. The property is currently zoned Exclusive Farm Use - 20
(EFU-4) Zone.
6. The subject property is generally level and is used as an
airport facility with runways, hangars, and miscellaneous
accessory uses. That those portions of the property
undeveloped are used for other airport -related uses.
7. The surrounding property is currently zoned either Exclusive
Farm Use - 40 (EFU-3) Zone, Exclusive Farm Use - 20 (EFU-4)
Zone, or Multiple Use Agriculture (MUA) Zone.
7 - FINDINGS AND DECISION
EXHIBIT "B"
I
OL -43PAGE 969
8. The surrounding property is primarily used for agricultural
uses. The Bend Municipal Airport has been used as an Airport
since 1942.
9. Considerable investment has been made in the Airport site,
and it appears that there is a commitment to continue the use
of the Airport for the next twenty years.
10. The Bend Municipal Airport could not be relocated to any
other site.
11. The Bend Municipal Airport complements the Redmond Airport
since they have differing functions.
12. That all public agencies involved in the Airport and the
users of the Airport have relied on its continued existence
and capability to meet general requirements of the area.
13. The Airport will continue as a general aviation facility
which will develop to mee the growing needs of the community
for such a transportation facility.
14. The subject property is designated as a airport in the
Deschutes County Year 2000 Ccomprehensive Plan map.
15. Ordinance No. 80-221 adopted Airport Development (AD) Zone to
be applied to airports within Deschutes County.
16. Ordinance No. 80-222 added an amended policy to the Deschutes
County Year 2000 Comprehensive Plan recognizing the Bend
Airport, taking an exception to Agricultural Goal 3 for the
Airport, and recognizing the Airport Master Plan for future
development of said Airport.
17. Land Use Board of Appeals has upheld the adoption of the
Airport Development (AD) zoning, and has approved the
Comprehensive Land Use Plan policies relating to the Bend
Airport. That the Land Conservation and Development Com-
mission found the Airport Development Zone and the plan
policies relating to the Bend Municipal Airport as being
consistent with Statewide planning goals.
CONCLUSIONS
1. The Application is in conformance with the Deschutes County
Year 2000 Comprehensive Plan.
2. There is a public need for the zone change. If the zoning is
not changed to Airport Development (AD) Zone, the Airport
will continue as a non -conforming use. This would make the
8 - FINDINGS AND DECISION
EXHIBIT "B"
} VOL .10. 43pw 963
Airport out of conformance with the Year 2000 comprehensive
Plan, since it could not be used as outlined in the policies
of the Comprehensive Plan.
3. The need is best served in its present location. It would be
virtually impossible to locate the Airport in another loca-
tion, the current Airport has been developed at its present
location since 1942, and the City of Bend has expended over
$600,000.00 for improvements to the Airport.
4. The applicant has met its burden of proof that the 340 acres
comprising the Airport should be rezoned, and that the need
for the Airport is best met in its specific location.
DECISION
The application is hereby approved.
od "
DATED this 23 rday of Alk, 1982.
ICK QU KEN USH, Chairman
9 — FINDINGS AND DECISION