BEFORE THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES COUNTY, OREGON
An Ordinance Amending Ordi-
nance No. PL -15, Deschutes
County Zoning Ordinance of
1979, As Amended, To Prohibit
Hydroelectric Facilities In
Designated Zones and Stretches*
Of The Deschutes River And Its*
Tributaries, To Allow Hydro-
electric Facilities As Condi-
tional Uses In Designated
Zones and Stretches of the
Deschutes River, Establishing
Conditional Use Criteria,
Adopting Findings And Conclu- *
sions, and Declaring An Emer- *
gency.
} i t
:
1' ; vUL 72 FArE3�
key"'.
coxvcF"
1986
ORDINANCE NO. 86-018
THE BOARD OF COUNTY COMMISSIONERS OF DESCHUTES COUNTY,
OREGON, ORDAINS as follows:
Section 1. Section 1.030, Ordinance No. PL -15, Deschutes
County Zoning Ordinance of 1979, as amended, is further amended
to include the following definitions:
"(25B) Conduit. Any tunnel, canal, pipeline,
aqueduct, flume, ditch or similar man-
made structure which is or may be used
to convey water.
(27A) Dam. Any man-made structure which is
or may be used to impound water.
(28A) Diversion. Any man-made structure
which is or may be used to deflect or
divert water from a river or stream
into a conduit.
(37A) Fish Passage Device. Any man-made structure
which is or may be used to enable fish
to pass over a dam to move upstream.
(37B) Fish Protection Device. Any man-made
structure, such as a fish screen, which
is or may be used to prevent fish from
entering into or passing through con -
1 - ORDINANCE NO. 86-018
voL 72
,A72
duits, penstocks and other water -con-
ducting structures or devices connected
to a hydroelectric facility.
(53A) Hydroelectric Facility. All aspects of
any project or development necessary
for or related to the generation of
hydroelectric energy, including, but
not limited to, conduits, dams, diver-
sions, fish ladders and screens, gen-
erators, impoundments, penstocks,
turbines, transmission facilities, and
related buildings, structures, storage
areas, access roads, parking areas and
surrounding and adjacent lands which
are necessary for or related to the
facility.
(53B) Impoundment. Any man-made structure
which is or may be used to impound
water.
(85A) Penstock. Any conduit or other struc-
tur— e w ich is or may be used to convey
water to the driving mechanism of the
generator.
(130A) Transmission Facility. The conductors,
lines, poles, towers, structures,
corridors and construction staging and
assembly areas necessary for or asso-
ciated with the transmission of elec-
tricity from a hydroelectric facility
for distribution."
Section 2. Subsection 134, Section 1.030, Ordinance No. PL -
15, Deschutes County Zoning Ordinance of 1979, as amended, is
further amended to read as follows:
"(134) Utility Facility. Any major struc-
tures, excluding hydroelectric facil-
ities, owned or operated by a public,
private or cooperative electric, fuel,
communications, sewage or water company
for the generation, transmission,
distribution or processing of its prod-
ucts or for the disposal of cooling
water, waste or by-products, and inclu-
ding power transmission lines, major
trunk pipelines, power substations,
water towers, sewage lagoons, sanitary
landfills and similar facilities, but
2 - ORDINANCE NO. 86-018
VOL 72 PAGE 373
excluding local sewer, water, gas,
telephone and power distribution lines,
and similar minor facilities allowed in
any zone."
Section 3. Subsection 3, Section 4.010, Exclusive Farm Use
- EFU 320, Ordinance No. PL -15, Deschutes County Zoning Ordinance
of 1979, as amended, is further amended by the addition of the
following:
"(0) Hydroelectric facility, in accordance with Sec-
tions 5.210 and 8.050(22) of this Ordinance."
Section 4. Subsection 3, Section 4.020, Exclusive Farm Use
- EFU 80, Ordinance No. PL -15, Deschutes County Zoning Ordinance
of 1979, as amended, is further amended by the addition of the
following:
"(0) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 5. Subsection 3, Section 4.030, Exclusive Farm Use
- EFU 40, Ordinance No. PL -15, Deschutes County zoning Or finance
of 1979, as amended, is further amended by the addition of the
following:
"(0) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 6. Subsection (3), Section 4.040, Exclusive Farm
Use - EFU 20, Ordinance No. PL -15, Deschutes County Zoning Ordi-
nance of 1979, as amended, is further amended by the addition of
the following:
"(P) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 7. Subsection 3, Section 4.060, Multiple Use Agri-
cultural Zone - MUA, Ordinance No. PL -15, Deschutes County Zoning
Ordinance of 1979, as amended, is further amended by the addition
of the following:
"(T) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section B. Subsection 3, Section 4.070, Forest Use F-1,
Ordinance No. PL -15, Deschutes County Zoning Ordinance of 1979,
as amended, is further amended by the addition of the following:
3 - ORDINANCE NO. 86-018
VOL 72 PACE!''
"(B) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 9. Subsection 3, Section 4.080, Forest Use F-2,
Ordinance No. PL -15, Deschutes County Zoning Ordinance of 1979,
as amended, is further amended by the addition of the following:
"(0) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 10. Subsection 3, Section 4.085, Forest Use F-3,
Ordinance No. PL -15, Deschutes County Zoning Ordinance of 1979,
as amended, is further amended by the addition, of the following:
"(P) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 11. Subsection 3, Section 4.100, Surface Mining
Zone - SM, Ordinance No. PL -15, Deschutes County Zoning Ordinance
oflamas amended, is further amended by the addition of the
following:
"(F) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 12. Subsection 3, Section 4.110, Surface Mining
Reserve Zone - SMR, Ordinance No. PL -15, Deschutes County Zoning
Ordinance of 1979, as amended, is further amended by the addition
of the following:
"(F) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 13. Subsection 3, Section 4.120, Rural Residential
- RR -10, Ordinance No. PL -15, Deschutes County Zoning Ordinance
of1979, as amended, is further amended by the addition of the
following:
"(P) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 14. Section 4.195, Deschutes River Combining Zone -
DR, Ordinance No. PL -15, Deschutes County Zoning Ordinance of
1979, as amended, is repealed.
4 - ORDINANCE NO. 86-018
VOL 72 PAGE 37 5
Section 15. Subsection 3, Section 4.220, Rural Industrial
Zone - RI, Ordinance No. PL -15, Deschutes County Zoning Ordinance
of 1979, as amended, is further amended by the addition of the
following:
"(P) Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 16. Subsection 2, Section 4.240, Planned Community
Zone - PC, Ordinance No. PL -15, Deschutes County Zoning Ordinance
o 1979 -, as amended, is amended by the addition of the following:
"(E)2.f. Hydroelectric facility, in accordance with
Sections 5.210 and 8.050(22) of this Ordi-
nance."
Section 17. Article 5, Ordinance No. PL -15, Deschutes
County Zoning Ordinance of 1979, as amended, Supplementary Pro-
visions, is amended by the addition of a new Section 5.210,
providing as follows:
"Section 5.210, Hydroelectric Facilities.
(1) No new hydroelectric facilities shall be
constructed, and no existing hydroelectric
facilities shall be enlarged or expanded in
size of area or generating capacity, on the
following rivers and streams within Deschutes
County:
(A) Deschutes River, from its headwaters
to River Mile 227, above but not in-
cluding Wickiup Dam, and from Wickiup
Dam to River Mile 171 below Lava
Island Falls;
(B) Crooked River;
(C) Fall River;
(D) Little Deschutes River;
(E) Spring River;
(F) Paulina Creek;
(G) Squaw Creek;
(H) Tumalo Creek.
5 - ORDINANCE NO. 86-018
VOL 72 RAGE 376
(2) Hydroelectric facilities are allowed as a
conditional use on the Deschutes River at
Wickiup Dam, and from River Mile 171 below
Lava Island Falls downstream to the northern
Deschutes County line. Such conditional use
shall be governed by the conditions set forth
in Section 8.050 of this Ordinance."
Section 18. Section 8.050, Ordinance No. PL -15► Deschutes
County Zoning Ordinance of 1979, as amended, Conditional Uses, is
amended by the addition of a new subsection (22), providing as
follows:
"(22) Hydroelectric Facilities.
(A) The criteria set forth below shall apply to
any construction or expansion of, or other
modification to, hydroelectric facilities
in zones where such facilities are permit-
ted as a conditional use. A conditional
use permit may be granted for the construc-
tion or expansion of, or other modification
to, a hydroelectric facility only upon
findings by the Hearings Body that the pro-
posal meets each of the following criteria,
where applicable;
(1) The facility is located at and
physically connected to an exist-
ing man-made diversion or impound-
ment;
(2) The facility will not increase the
maximum surface area or capacity
of the impoundment created by the
existing dam or diversion to which
the facility will be connected;
(3) The facility will maintain or en-
hance, to the greatest extent pos-
sible, the existing scenic, visual,
environmental and aesthetic quali-
ties of the affected stretch of the
river.
(4) The facility will maintain or
enhance the existing recreational
opportunities on or adjacent to
the affected stretch of the river.
(5) The facility will maintain or en-
hance existing fish and wildlife
6 - ORDINANCE NO. 86-018
VOL 72 FACE 3 `7
habitat, and will have no adverse
impact upon any threatened or en-
dangered fish, wildlife or plant
species or their habitat.
(6) The facility and its operation will
maintain or enhance existing water
quality in the affected stretch of the
river, except during construction of the
facility, when adverse impacts on water
quality will be minimized. Specifi-
cally, the facility and its operation
will not:
(a) deposit, or create a zone for
the deposit of, sediments in the
river at or adjacent to the
site;
(b) increase the temperature of the
river in the affected stretch by
any means, including but not
limited to removal of vegetation
or reduction in streamflow; or
(c) create the potential for, or
result in, spillage, leakage or
discharge of oil, chemicals or
other substances or waste prod-
ucts which could reach the
river.
(7) The facility and its operation will not
increase soil or bank erosion or destroy
bank habitat at or on land adjacent to the
site, except during construction of the
facility, during which time soil or bank
erosion and destruction of bank habitat
will be minimized.
(8) The facility and its operation will
maintain existing public access to
the affected stretch of the river.
(9) The facility will not be located at
or immediately adjacent to any iden-
tified archaeological or historical
site, national or state park, wild-
life refuge, Bureau of Land Manage-
ment Outstanding Natural Area or Area
of Critical Environmental Concern,
7 - ORDINANCE NO. 86-018
VOL 72 PscE 278
Federal Research Natural Area or U.S.
Forest Service Special Interest Area.
(10) The facility will not be located on
any stretch of the river that is
being studied or recommended for
inclusion in either the Federal Wild
and Scenic Rivers Program or the
State Scenic Waterways Program,
unless location of the facility at
that site would not preclude inclu-
sion of the stretch in the state or
federal program.
(11) The facility and its operation will
comply with all applicable noise,
water quality and pollution regu-
lations of the Oregon Department of
Environmental Quality.
(12) The facility and its operation will
comply with all applicable state and
local fill -and -removal statutes and
regulations.
(B) The applicant for a conditional use permit
for a hydroelectric facility, in addition
to all other requirements, shall submit the
following for approval:
(1) Detailed construction plans and
profiles of all facility features,
including building elevations of the
powerhouse and other structures,
excavation plans and narrative as to
where blasting will occur and where
excess material will be deposited, and
landscaping and reclamation plans.
(2) Detailed plans for meeting the cri-
teria set forth in subsection (A)
above.
(3) Detailed plans for river enhancement
documenting both on-site and off-site
enhancement plans consistent with
adopted river -related goals and poli-
cies, such as plans and methods for
conserving water and enhancing stream -
flows. The plan shall identify costs,
time schedules and coordination activ-
8 - ORDINANCE NO. 86-018
. VOL 72 PA ._ b-9
ities with affected persons and agen-
cies for such enhancement plans.
(4) A cash deposit, performance bond or
other security acceptable to Deschutes
County, in an amount equal to 100
percent of the estimated cost of river
enhancement.
(5) Detailed plans for a water conserva-
tion and stream enhancement program to
be funded by a portion of revenues
generated by the operation of the
proposed facility. The program plans
shall contain the following:
(a) A program timetable;
(b) Projected gross revenues from
the proposed facility;
(c) Projected program expenditures
and the percentage of gross
revenues they represent;
(d) Projected water savings and the
percentage of known current
water losses they represent;
(e) A declaration by the applicant
that at least fifty percent of
the conserved water will remain
undiverted by the applicant;
(f) A declaration by the applicant
that water diversion for power
generation will not cause water
flow in the affected stretch of
the river (from the diversion to
the tailrace exit) to fall below
the minimum streamflow for that
stretch as recommended by the
Oregon Department of Fish and
Wildlife; and
(g) A declaration by the applicant
that it will enter into an
agreement with Deschutes
County, prior to beginning
construction of the facility,
by which the applicant agrees
to fulfill all of the require -
9 - ORDINANCE NO. 86-018
VOL 72 38
ments in paragraphs (a) through
(f) of this subsection."
Section 19. The Board of County Commissioners adopts as its
findings and conclusions supporting the amendments in Sections 1
through 18 of this Ordinance the Staff Report, dated May 21,
1986, relating to the Deschutes River Corridor.
Section 20. This Ordinance being necessary for the imme-
diate preservation of the public peace, health and safety, an
emergency is declared to exist, and this Ordinance takes effect
on its passage.
DATED this day of June, 1986.
ATTEST:
Recording Secretary
10 - ORDINANCE NO. 86-018
BOARD OF COUNTY COMMISSIONERS
OF 019SCHUTF� COUNTYj/'O EGON
OLV BRISTOW PRANTE, Chair
Commissioner
, Commissioner