HomeMy WebLinkAboutRoad & Road Capital Improvement PlanRoad Department
Presenters:
Chris Doty, PE, Director
Cody Smith, Asst. Director/
County Engineer
▪FY25 Proposed Budget Presentation
Budget Committee Meeting | May 23, 2024
Agenda
Introductions
Budgeting Priorities
Revenue Assessment
FY 25 Budget Review –major
programs
Transportation CIP
Please ask questions at any
time !
Department Overview
61.0 Full Time Employees (FY 25, -1 from FY 24) plus Contract Seasonal Employees
We strive to
maintain the quality
and improve the
experience for all
users of the
Deschutes County
transportation
system.
Budgeting Priorities
#1
•Maintain the system
•Pavement Management Program: Sustained PCI.
•Signing/Striping
•Vegetation Management
•Shoulder Maintenance
•Bridge Maintenance
#2
•Operate the system
•Snow/Ice
•Roadside Hazards
•Event/Incident Response
•Fleet/Equipment
#3
•Improve the system
•Capital Projects
•Major Maintenance
•Safety Improvements
•Modernization
Road Department Fund Summary
Revenue:
•State/Fed
•Operations and Services (Cities)
•ISF (County Departments, Surveyor)
•External (contract work, outside
agencies)
Expenses:
•Personnel (all Road Dept)
•Materials/Services /Supplies
(operating expense)
•CIP Contribution and Pavement
Preservation Contribution to 465 Fund
•Equipment/Building contribution to
330 Fund
The Operating Fund for the
Road Department
Surveyor and Corner
Fund
Revenue:
•Surveyor Fees
•Recording Fees
Expenses:
•Reimburse 325 for
Personnel, Mtls,
Supplies, etc
Building and Equipment
Revenue:
•Transfer from 325
Expenses:
•Equipment per
replacement schedule
•Building improvements
as needed
•Reserves
Transportation SDC
Revenue:
•SDC Fee Revenue
Expenses:
•Transfer to 465 on a
per project basis.
Transportation CIP
Revenue:
•Contribution from
325
•Transfer from 336
Expenses:
•CIP Projects
•Bridge Replacement
•Major Maintenance
•Pavement Pres.
Vehicle
Maint./Replacement
Revenue:
•Interfund Trans from
other departments
Expenses:
•Reimburse 325 for
Maintenance
•Purchase new fleet
DC Road Agency
Revenue:
•SRS Funding
Expenses:
•Transfer to 325
325 Fund: Global Detail
Beg Working
Cap
16%
State Gvt
Payments
66%
Federal Gvt
Payments
11%
Partnership
Revenue
2%
Interfund
Charges
4%
Other
Categories
1%
Personnel
Services
29%
Materials/Services
31%
Transfers Out
33%
Contingency
7%
RESOURCES REQUIREMENTS
Funding Source FY 25 Budget (FY 24)Funding Outlook/Comments
State Highway Fund Allocation $21.5M ($20.6M)Full phase-in of HB 2017 fuel tax phasing.
PILT $2.7M ($2.4M)Includes added PILT due to HB 2174. Re-
authorized for FY 25.
SRS $0.68M ($0.66M)Pending federal re-authorization.
FEX (formerly STBG)$0.88M (0.89M)Fund Exchange revenue per HB 2101
(direct to Fund 465)
SDC $1.5M ($1.5M*)Updated SDC rate in FY 25 to reflect new
CIP needs (funds applied to qualified CIP
projects via Fund 465), *Actuals trending
lower.
Grants $0.14M ($0.34M)Federal SS4A grant to update TSAP
Partnership $0.74M ($0.8M)Reimbursement for various services.
Revenue Assessment/Outlook
FY 25 Budget Highlights
1. Pavement Management Program (chip seal, overlay,
crack seal, patch):
77 miles of chip seal (DC System) $2.4M (materials)
City of Redmond
City of Sisters
10+/-miles of Slurry Seal, various neighborhoods. ($0.35M)
Crack Seal, Patch, and leveling course (DC system), $0.43M
8.5+/-miles of overlay ($6.2M)
Total Program: $9.6M (DC System)
Sustains Pavement Condition Index in low 80s (with $0
deferred maintenance )
2 . Payment to City of Redmond, $500,000, for
wastewater treatment capacity at Redmond Wetlands
Complex to provid e capacity for Terrebonne (PILT
funded).
#1
Personnel#2
Building and Equipment: 330 Fund#2
Facility Electrical System Update 300,000$
Office HVAC 100,000$
Decant Facility Design 50,000$
Negus Sand Shed and Shop 650,000$
Truck Barn 50,000$
Main Campus EV Charging Stations 30,000$
Replacement Shop Crane 32,000$
Replacement Fuel Pumps-Bend 175,000$
Total 1,387,000$
Building and Site
Building and Equipment: 330 Fund#2
•Total 330 Fund Expenditures:
•$4,313,056
•Transfer from 325 Fund:
•$2,089,362
•Reserve:
•$4,099,386
Belly Dump Tractor 156,871$
Upfit 3 Tractors to Sanders Labor/Hydraulics. 300,000$
Belly Plow 14,000$
Belly Plow 14,000$
Wing Plow: Move from FY 24 to FY25 20,000$
Wing Plow: Move from FY 24 to FY25 20,000$
Wing Plow 20,000$
Wing Plow 20,000$
12 Ft 2-Way Snow Plow: Move from FY 24 to FY25 22,000$
Large Motor Grader 575,000$
12/15 Yard Dump Truck 285,000$
12/15 Yard Dump Truck 285,000$
12/15 Yard Dump Truck 285,000$
Mechanical Street Sweeper 400,000$
Sander 50,000$
Sander 50,000$
Mastic Machine 80,000$
Vehicles/Pickups 125,000$
Upfit 30,000$
Total 2,751,871$
Equipment
Fund 325: Five year projection
Per internal Road Department budget model. Assumes moderate revenue increase in FY 27
associated with a proposed/anticipated 2025 legislative transportation funding package.
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
Ending Working Capital $ 5,223,706 $ 2,506,098 $ 2,581,281 $ 2,658,719 $ 2,738,481
Revenue
Beginning Working Capital $ 5,223,706 $ 2,433,105 $ 2,506,098 $ 2,581,281 $ 2,658,719
All other Revenues 27,479,906 27,888,063 30,941,491 31,985,751 33,030,864
Total Revenue $ 32,703,612 $ 30,321,168 $ 33,447,589 $ 34,567,032 $ 35,689,584
Expenditures
Personnel $ 9,556,843 $ 9,843,548 $ 10,138,855 $ 10,443,020 $ 10,756,311
Materials and Services 9,992,969 10,292,758 10,601,541 10,919,587 11,247,175
Capital -100,000 100,000 100,000 100,000
Debt Service -----
Transfers Out 10,720,695 7,578,763 10,025,912 10,445,705 10,847,617
Total Expenditures $ 30,270,507 $ 27,815,069 $ 30,866,308 $ 31,908,313 $ 32,951,103
Ending Working Capital $ 2,433,105 $ 2,506,098 $ 2,581,281 $ 2,658,719 $ 2,738,481
$-
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
Five-Year Forecast
Ending Working Capital Minimum Working Capital Policy
….to the CIP
Road Capital
Improvement Plan (CIP)
Presenter:
Cody Smith, Asst. Director/
County Engineer
▪FY24-24 Proposed Budget Presentation
Budget Committee Meeting | May 23, 2024
FY24-25 Road CIP
•Road CIP Fund Revenue
Contract pavement preservation projects identified in
Department’s Pavement Management System
ROAD CIP FUND
465
•“Trickle-down” –
maintenance/ operations
first
•Remainder towards capital
improvements
•Dedicated to TSP-
identified projects based
on SDC policy
•Typically coincide with
state/federal TIP cycles
•Programs include:
•Fund Ex
•LBP
•FLAP
•ARTS
FY24-25 Road CIP
•Road CIP Fund Revenue
Contract pavement preservation projects identified in
Department’s Pavement Management System
ROAD CIP FUND
465
$8,631,333
$ 881,339
BEGIN FUND $ 15,534,050
INTEREST $ 475,310
TOTAL REVENUE
$27,522,032
$ 2,000,000
FY24-25 Road CIP
•Categorized into 4 programs:
TRANSPORTATION SYSTEM -
PAVEMENT PRESERVATION -
TRAFFIC SAFETY -
BRIDGE CONSTRUCTION -
Major road improvement projects identified in TSP,
special studies, intergovernmental agreements
Contract pavement preservation projects identified in
Department’s Pavement Management System
Contract safety improvements, including signage,
guardrail, and delineation, to bring features up to current
state and federal standards
Bridge replacement and rehabilitation projects identified in
Department’s Bridge Management System
FY24-25 Road CIP
•FY Proposal
TRANSPORTATION SYSTEM -$ 7,188,512
PAVEMENT PRESERVATION -$ 6,510,000
TRAFFIC SAFETY -$ 400,000
BRIDGE CONSTRUCTION -$ 2,090,500
FY 2025 CIP PROJECT TOTAL =$ 16,189,012
FY24-25 Road CIP
•$16.1 Million in local transportation infrastructure improvements
$4.4 Million in intersection safety/capacity improvements
$8.7 Million in pavement preservation
$2 Million in bridge replacement
$0.8 Million in bicycle/pedestrian improvements
FY 23-24 Road CIP –Completed Projects
•Hunnell Road: Bend City Limits to Tumalo Road Improvement
•Scope of Work: Improvement and
realignment of 3.7 miles of collector
road, including new canal crossing
bridge
•Total Cost: $6,158,750
FY 23-24 Road CIP –Completed Projects
•Deschutes Market Road/Hamehook Road Roundabout
•Scope of Work: Roundabout
construction
•Total Cost: $2,403,471
FY 23-24 Road CIP –Completed Projects
•Old Bend Redmond Hwy: US20 to Tumalo Rd Paving
•Scope of Work: Paving and
delineation
•Total Cost: $1,295,556
FY 23-24 Road CIP –Completed Projects
•Rosland Rd / Wendy Rd / Tracy Rd Reconstruction and Paving
•Scope of Work: Full-depth
reconstruction and paving around La
Pine Travel Center
•Total Cost: $647,291
FY 23-24 Road CIP –Completed Projects
•Butler Market Rd and Dickey Rd Paving
•Scope of Work: Paving and
delineation
•Total Cost: $1,455,806
FY 23-24 Road CIP –Completed Projects
•Gribbling Road Bridge Replacement
•Scope of Work: Bridge replacement
•Total Cost: $675,452
•ODOT LBP Funding $606,083
FY 23-24 Road CIP –Work in Progress
•Spring River Rd: S Century Dr to USFS Boundary Paving
•Scope of Work: Paving and delineation
•Status:
•Under construction
•May 31, 2024 completion
•Total Cost: $1,100,000
FY 23-24 Road CIP –Work in Progress
•Smith Rock Way Bridge Replacement
•Scope of Work: Bridge replacement
•Status:
•Under construction
•June 30, 2024 completion
•Total Cost: $1,118,208
FY24-25 Road CIP
•Powell Butte Highway/Butler Market Road Roundabout
•Scope of Work: Roundabout
construction at arterial intersection
•Status:
•Under Construction
•August 2024 completion
•Estimated Cost:
•FY22 (actual)$ 38,562
•FY23 (actual)$ 250,902
•FY24 $1,348,980
•FY25 $1,095,760
•Total $2,734,204
FY24-25 Road CIP
•NW Lower Bridge Way/NW 43rd Street Intersection Improvement
•Scope of Work:
Intersection improvement
•Status:
•Virtual Open House –4/19
•Design/NEPA for Roundabout
alternative in process
•Anticipated construction start in
Summer 2025
•Estimated Cost:
•FY23 (actual)$ 10,670
•FY24 $ 159,140
•FY25 $1,650,000
•FY26 $1,000,000
•Total $2,819,810
FY24-25 Road CIP
•Tumalo Reservoir Road: OB Riley Road to Sisemore Road
Improvement
•Scope of Work: Full-depth
reclamation, widening, and paving
•Status:
•Under design
•Anticipated construction in
Summer 2025
•Estimated Cost:
•FY24 $ 200,000
•FY25 $2,417,752
•FY26 $2,489,000
•Total $5,106,000
FY24-25 Road CIP
•S Century Drive: Sunriver Corridor Intersection Improvements
•Scope of Work:
•Refinement planning and public
engagement
•Intersection improvements
•S Century Dr/Venture Ln (Loop)
•S Century Dr/Spring River Rd
•S Century Dr/Huntington Rd
•Status: Design contract award
•Estimated Cost:
•FY24 $ 526,000
•FY25 $ 1,650,000
•FY26 $ 2,977,000
•FY27 $ 5,138,000
•Total $10,291,000
S Century Dr/Venture Ln Concept
S Century Dr/Spring River Rd Concept
S Century Dr/Huntington Rd Concept
FY24-25 Road CIP
•Northwest Way/NW Coyner Ave Intersection Improvement and
Paving
•Scope of Work:
•Left-turn lane construction
•Paving of Northwest Way,
Altmeter Ave, and Sedgwick
Ave
•Status: Design start in Fall 2024
•Estimated Cost:
•FY25 $ 85,000
•FY26 $1,035,000
•FY27 $ 948,100
•Total $3,068,100
FY24-25 Road CIP
•La Pine Stormwater UIC Improvements
•Scope of Work:
•Install pre-treatment systems for storm
water drywell inlets
•Construct biofiltration swales to replace
infiltration galleries
•Compliance with County’s DEQ UIC Permit
•Status:
•Delayed due to scope change
•Spring 2025 Construction
•Estimated Cost: $240,000
FY24-25 Road CIP
•Pavement Preservation
MAJOR PAVING PROJECTS
Road Begin End FY24 Cost FY25 Cost FY26 Cost Total Cost
Old Bend
Redmond Hwy/ S
Canal Blvd
Tumalo Rd Helmholtz Rd $880,000 $2,520,000 -$3,400,000
Deschutes Market
Rd/Tumalo Rd
19th St Tumalo Pl -$520,000 -$520,000
Horse Butte Rd Arnold Mkt Rd USFS
Boundary
-$630,000 -$630,000
Powell Butte Hwy McGrath Rd US 20 -$2,290,000 $350,000 $2,640,000
MINOR SURFACING PROGRAMS
Pavement Surfacing Treatment FY24 Cost FY25 Cost FY26 Cost
Slurry Seal $657,325 $350,000 $350,000
Misc. Local Roads Paving -$500,000 $500,000
FY24-25 Road CIP
•Hamehook Road Bridge Replacement
•Scope of Work: Bridge replacement
•Status:
•90% Design
•Late 2024 Construction Start
•Estimated Cost:
•FY 2024 $ 365,000
•FY 2025 $1,930,500
•Total $2,295,500
FY24-25 Road CIP
•Wilcox Avenue Bridges Removal
•Scope of Work: Bridge removal (X2)
and road reconstruction
•Status:
•Presently detour for Smith Rock
Way Bridge Replacement project.
•Ongoing coordination with Lone
Pine, Three Sisters, and Central
Oregon Irrigation Districts
•Start Design in Fall 2024
•Spring 2025 Construction
•Estimated Cost:$160,000
FY24–FY28 -5-Year Road CIP
TRANSPORTATION SYSTEM -$35,267,412
PAVEMENT PRESERVATION -$24,430,000
TRAFFIC SAFETY -$ 1,700,000
BRIDGE CONSTRUCTION -$ 7,178,500
5-YEAR CIP PROJECT TOTAL -$ 68,855,912
Thank you