HomeMy WebLinkAboutF0112 Courthouse Follow Up Report PUBLISHED (6-23-25)To request this information in an alternate format, please call (541) 330-
4674 or send email to internal.audit@Deschutes.org
Follow-up on Courthouse Pre-Construction Audit:
Improved procedures for risk assessment and
oversight will increase the likelihood of projects
delivered on budget and on time.
June 2025 Our 2024 audit of the Courthouse pre-construction phase highlighted
both strengths and areas for improvement in the Facilities
Department’s approach to managing capital construction projects.
Nine months later, the Department is in a better position to ensure
that large projects are delivered on schedule and on budget. The
Department developed a Construction Manual with improved
practices for risk assessment and oversight. It also took steps towards
improving construction manager/general contractor contract language
to hold the contractor accountable and control costs.
Deschutes County Office of the Internal Auditor Page 1 of 3
Audit Follow-up Report: June 2025
Courthouse Pre-Construction Audit
Recommendation Status Key:
Initial finding: The courthouse project experienced delays in all preconstruction
phases; none were completed according to the original duration.
Initial timelines did not incorporate the complexity of managing
multiple stakeholders and the regulatory risks and challenges
associated with permitting. Risks arising from the complexity of
the courthouse project could have been more effectively
identified, assessed, and mitigated using a risk register.
Recommendation: The Facilities Department should implement a comprehensive
pre-construction planning and risk management framework.
Update: The Facilities Department developed a Construction Management
Manual based on the Project Management Body of Knowledge.
The approach to risk defined in the Manual includes assessing
risk, creating a risk register, and addressing risks.
3
Resolved
0
In Process
0
Accept Risk
Management addressed risk.
Auditors will no longer monitor.
Recommendations are in
progress. Auditors will continue
to monitor.
Management accepted the risk of
not implementing the
recommendation.
Risk management framework adopted.
Deschutes County Office of the Internal Auditor Page 2 of 3
Audit Follow-up Report: June 2025
Courthouse Pre-Construction Audit
Initial finding: Several inconsistencies in adhering to contract language were
noted during the audit: detailed receipts and documentation
were not consistently provided for reimbursement; a clerical error
in the contract indicated that the contractor was underinsured;
and the life-size courtroom mockup project was performed
without being in the scope of work. Facilities did not formally
assign roles and responsibilities allowing for overlaps, conflicts,
and potential miscommunication within the project team.
Recommendation: The Facilities Department should develop and implement
comprehensive policies and procedures to strengthen guidelines
and oversight for capital projects.
Update: The Facilities Department developed a Construction Management
Manual based on the Project Management Body of Knowledge.
The Manual directs staff to assemble a construction team with
assigned roles and clear expectations.
Initial finding: Without clear and definitive contract language the County
exposed itself to significant risks, including potential overpricing
and reduced value. The contract did not include defined allowable
costs, requirements for crediting rebates or savings to the
County, or obligations to notify the County about using
contingency funds. Additionally, contract language did not reflect
the department’s efforts to support under-represented business
owners.
Recommendation: The Facilities Department should coordinate with County Legal to
create a construction manager/general contractor contract and
general conditions template with enhanced cost controls and
consistent equity support.
Clearer roles will improve oversight.
Staff research will result in improved contract
language.
Deschutes County Office of the Internal Auditor Page 3 of 3
Audit Follow-up Report: June 2025
Courthouse Pre-Construction Audit
Update: At the time of the follow-up, the Facilities Department was not
planning a similar contract model for any near-term projects.
Instead of investing resources in developing a template, staff
researched other contracts from several Oregon public entities
and planned to use them as a starting point for a new template to
be developed when the next construction manager/general
contractor project is under consideration.
Next Steps: With all recommendations resolved, we will not
report on the status of audit recommendations in our Global
Follow-up Report. However, we are planning to conduct a post-
construction audit of the courthouse project after its anticipated
completion in the Summer of 2026.
Deschutes County Office of the Internal Auditor
Audit Follow-up Report: Courthouse Preconstruction
The mission of the Office of Internal Audit is to improve the performance of Deschutes
County government and to provide accountability to residents. We examine and
evaluate the effectiveness, efficiency, and equity of operations through an objective,
disciplined, and systematic approach.
The Office of Internal Audit: Audit committee:
Elizabeth Pape – County Internal Auditor Daryl Parrish, Chair – Public member
Susan DeJoode – Performance Auditor Phil Anderson – Public member
Jodi Burch – Public member
Phone: 541-330-4674 Joe Healy – Public member
Email: internal.audit@deschutes.org Summer Sears – Public member
Web: www.deschutes.org/auditor Kristin Toney – Public member
Patti Adair, County Commissioner
Charles Fadeley, Justice of the Peace
Lee Randall, Facilities Director
If you would like to receive future reports and information from Internal Audit or
know someone else who might like to receive our updates, sign up at
http://bit.ly/DCInternalAudit.